37 Critical document templates for Principal Contractors: User Manual Index
Purpose and outcome (what it’s for)
This guidance-note explains how to use the RAMS Compliance Spot Check & Intervention Record during live work to prove that:
- the approved RAMS is actually being followed on site (not just filed),
- the supervisor is actively checking and stepping in early when the job drifts, and
- any issues are corrected, briefed, and followed up properly.
Good completion looks like: short factual notes, clear actions taken, names of who agreed/actioned, and a decision on whether the RAMS needs updating and/or a re-brief.
Who uses it (roles and responsibilities)
| Role | What they do |
|---|---|
| Supervisor / Working foreman | Completes the spot check, records what was seen, intervenes if needed, and starts any follow-up actions. |
| Operative / Lead hand | Confirms they’ve been briefed and agrees the actions taken (sign-off where used). |
| Site manager / Contracts manager | Reviews spot checks (especially any “No” answers, stoppages, or repeat issues), supports escalations, and ensures RAMS updates happen. |
| H&S adviser (if you have one) | Samples records for trends, checks quality, and helps improve RAMS and supervision controls. |
When to use it (trigger points and frequency)
Use it for quick checks during live work, especially where things can drift quickly:
- hot works (grinding, cutting, welding, roofing torches),
- lifting operations (telehandler, crane, chains, slings),
- work at height (scaffold, MEWP, ladders, roof work, openings),
- breaking out / cutting / chasing,
- openings and edges,
- any job with multiple trades working close together.
Good times to do a spot check
- Start of task (first set-up): barriers, permits, tools, brief.
- After a change: new operatives, different workface, weather change, different plant/tool.
- After a near miss, complaint, or “that was close”.
- Mid-task: when attention drops and shortcuts creep in.
Frequency (practical rule): for higher-risk tasks, aim for at least one spot check per crew per shift (more if the job is changing). For routine lower-risk work, sample regularly and focus on change points.
Before you start (what you need to have to hand)
- The approved RAMS for the exact task (right version/date).
- Permits where applicable (e.g., hot works permit, permit to dig, lifting plan/permit if used on your sites).
- Evidence of competence if the task needs it (e.g., CPCS/NPORS, PASMA, IPAF, abrasive wheels, confined spaces, first aid).
- Pre-use checks where relevant (MEWP checks, lifting gear inspections, fire extinguisher in date, RCD checks).
- Knowledge of what “good” looks like for the specific job step you’re observing (sequence, barriers, exclusion zone, supervision arrangements).
Tip: Don’t try to check everything in detail every time. Pick the most relevant items for the task and the main ways it can go wrong.
How to complete it (step-by-step on site)
1) Fill in job and RAMS details
- Be specific with location (plot/bay/floor/area). It matters for investigations and follow-up.
- Record the RAMS reference and version/date. This is what proves you checked the right document.
- Write the task observed as the team would describe it (“cutting padstones”, “lifting steel beam”, “core drilling riser”, etc.).
2) Do the quick spot check (tick Yes / No / N/A)
- Tick Yes only if it’s actually in place and working (e.g., barrier is complete, not just “some cones”).
- Tick No if missing, not used, or not effective.
- Tick N/A only if it genuinely doesn’t apply to this task at this time (e.g., lifting controls when no lift is happening).
Make “No” mean something: every “No” should link to a note in “What I Saw” and an action in “Intervention” or “Follow-up”.
3) Record “What I Saw” (brief and factual)
- Observed work step: the exact moment you’re checking (e.g., “setting up the grinder”, “slinging the load”, “working at edge on deck 2”).
- What was happening: who/what/where (avoid opinions, keep it factual).
- RAMS says: the relevant control or sequence (one or two lines is enough).
- What differed: describe the drift/shortcut/missing control clearly.
Write it like a camera: “Two operatives cutting rebar with 9-inch grinder; no face shield; trailing lead across walkway” (not “unsafe cutting”).
4) Record “Intervention” (what you did on the spot)
- Tick the action(s) you actually took: reminder, stop job, add control, change method, swap tool/plant, re-brief, escalate.
- In “Details”, write what changed (e.g., “stopped work until fire watch in place and extinguisher brought to point of work”).
- Record who actioned/agreed (name or role if you don’t know the name).
If you stopped the job: note how it was made safe before you left the area (barriers, isolations, plant parked/keys removed, hot works ceased, etc.). If anything is still outstanding, record it and escalate.
5) Decide if the RAMS needs changing (or re-briefing)
- If the team drifted but the RAMS is still correct: you may only need a re-brief and supervision.
- If the workface or method has changed, or the RAMS doesn’t cover what’s happening: it likely needs an update.
- Assign who will update and a target date. If it’s urgent, don’t leave it as a future action—stop or control the work first.
6) Add follow-up actions (only if not closed out today)
- Keep actions specific and measurable (e.g., “Fit edge protection to opening at gridline B3” rather than “sort edge protection”).
- Put a clear owner and due date.
- Close out promptly and mark “Done” when completed.
7) Sign-off
- Supervisor signs to confirm the record is true and actions were taken.
- Operative/lead signs to confirm they understand what changed and any re-brief given.
Review and approval (what to check and when to escalate)
This record is mainly a supervisor tool, but it should be reviewed as part of normal site control.
Supervisor self-check (before filing)
- Does every “No” have a matching action or follow-up?
- Is it clear whether the job was made safe?
- Is the RAMS version/date recorded?
- Could someone else understand what happened from your notes?
Manager review (recommended)
- Review all records with stoppages, repeated issues, or RAMS not suitable.
- Check follow-up actions are being closed out.
- Look for trends (e.g., repeated PPE issues, barriers missing, poor briefings).
Escalate immediately if you see:
- a serious risk of injury (falls, lifting over people, uncontrolled hot works, live services),
- workers refusing to follow controls,
- RAMS clearly not matching the work,
- missing competence for high-risk tasks (no ticket/authorisation).
Recordkeeping (storage, retention, audit readiness)
- Where to store: keep with the job’s RAMS pack (site folder) and/or upload to your central H&S/project system.
- File naming (simple and searchable):
Project_Area_Task_YYYY-MM-DD_RAMS-SpotCheck_Supervisor - Link it to: the RAMS reference/version and any permit or lifting plan number where relevant.
- Retention: keep for the duration of the job and then in line with your normal project H&S file retention. If you’re unsure, a practical minimum is at least 3 years (longer if your client or insurer requires it).
Audit tip: a small number of well-completed spot checks beat a big pile of half-filled ones. Quality matters.
How often should this be reviewed or updated?
- On the day: close out actions or raise follow-ups before the shift ends where possible.
- Weekly: manager samples records to check trends and repeat issues.
- When RAMS changes: make sure the update is issued, the team is re-briefed, and the old version is removed from use.
Common mistakes (and how to avoid them)
- Tick-box only, no facts. Add 1–3 lines in “What I Saw” so the record stands up later.
- “No” with no action. If something is missing, record what you did and who fixed it.
- Wrong RAMS version. Always write the version/date. If the team has an old copy, swap it out and note it.
- Using N/A too often. N/A is fine, but don’t use it to avoid checking key controls for the task.
- Not naming who agreed/actioned. Names drive accountability and make follow-up easier.
- Not recording “made safe”. If you stopped work, write how the area was left safe before you walked away.
- Not feeding back into RAMS. If you see the same drift twice, the RAMS and/or briefing method likely needs improving.
Worked example (quick realistic scenario)
Scenario: Supervisor checks a team doing hot works cutting brackets off steelwork inside a partly finished unit.
- Quick spot check: RAMS on site (Yes), team briefed (Yes), hot works controls (No), housekeeping (No), public/other trades protected (Yes).
- What I saw: operative grinding near timber studs; no fire watch in place; extinguisher not at point of work; sparks landing into a corner with dust and offcuts.
- RAMS says: hot works permit required; clear combustibles; have extinguisher and fire watch during and after; contain sparks.
- Intervention: stopped job temporarily; cleared combustibles; brought extinguisher; set fire watch; issued/confirmed permit; re-briefed both operatives on spark containment and fire watch time.
- Made safe before leaving: Yes (area cleared, extinguisher in place, fire watch assigned).
- RAMS needs changing? No (RAMS suitable). Re-brief needed? Yes (controls not followed).
- Follow-up: check after 30 minutes fire watch completed and area signed off on permit.
Principal Contractor Support
Running a CDM Project as Principal Contractor?
Get the structure, advice, and documentation support you need to manage the role properly.
When you take on the Principal Contractor role, the responsibility for the Construction Phase Plan, site safety records, RAMS, and CDM compliance usually lands on the desk of a busy director or site manager.
CTC South West provides practical advisory support and structured systems that help you keep your documentation organised, your responsibilities clear, and your projects ready for client checks or audits.
Expert CDM support, site-ready documentation, and organised compliance records — all built around how construction projects actually run.
- Construction Phase Plans structured and ready for client review
- RAMS and project documentation tailored to your actual work
- Ongoing competent person support for Principal Contractors