Purpose and outcome (what good looks like)
This register is your site “source of truth” for what paperwork is live right now (drawings, specs, RAMS, permits, inspection forms, briefings/toolbox talks). It helps stop out-of-date information being used on site.
Good completion looks like:
- ✅ Everyone can quickly find the current revision of key documents.
- ✅ When a revision changes, the register shows what changed and who was told.
- ✅ Old prints and old PDFs are removed from work areas or clearly marked “superseded”.
- ✅ Weekly coordination meetings include a quick document check, and actions are recorded.
Who uses it (clear ownership)
| Role | What they do | Typical examples |
|---|---|---|
| Document Control Owner | Keeps the register up to date, updates the controlled copy pack, removes old versions. | Site Manager, Working Supervisor, Site Engineer. |
| Issuer / Designer / PC | Sends new revisions and confirms status (e.g., “for construction”). | Architect, Structural Engineer, Principal Contractor, Client rep. |
| Supervisors / Foremen | Checks the controlled copy is being used and briefs crews on changes. | Groundworks supervisor, Fit-out supervisor. |
| Subcontractors | Use only the current revision, raise queries if something doesn’t match. | M&E, Steelwork, Drylining, Roofing. |
| H&S / Quality support (if you have it) | Spot checks, helps with audit-ready filing and evidence of briefings. | External H&S adviser, QA manager. |
Tip: Even on small jobs, name one person as the Document Control Owner. If it’s “everyone”, it becomes “no one”.
When to use it (triggers and frequency)
- At site set-up / start of a new job: Create the first register and list the starting drawings/specs/RAMS.
- Every time a document changes: New revision received, new permit template, updated RAMS, revised inspection form.
- Before starting a new phase/area: Quick check that the right drawings and RAMS are current for that work.
- Weekly coordination meeting: Do the quick check and record actions.
- After an incident/near miss or design query: Confirm the team is working to the latest information and brief if needed.
Before you start (inputs and evidence you need)
- Latest drawing issue / transmittal from the designer/PC (email, CDE download notice, transmittal sheet).
- Document list for the job: drawings, specs, programme constraints, permits, inspection/test plans, RAMS, briefing records.
- Confirmed status for use (e.g., “for construction”, “for information only”). If unclear, treat as not live until confirmed.
- Agreed controlled copy arrangement:
- Paper: one controlled folder/box on site (e.g., site office) and one set where needed (e.g., workface folder) with strict change-out.
- Digital: one agreed folder path/platform (SharePoint/Dropbox/Google Drive/CDE) and one person responsible for uploads.
- Briefing method ready (pre-start, toolbox talk, supervisor briefing, noticeboard/email/WhatsApp) and a way to evidence it (attendance list, briefing record, photo of noticeboard, email chain).
How to complete it (step-by-step)
Step 1 — Set the basics (project details)
- Fill in the project, address, PC, and Site Manager.
- Assign a Document Control Owner (name a person, not a role).
- Write where the register is kept (folder/platform) and where the controlled copy is kept on site (exact place).
- Set a “reviewed up to” date each time you do the weekly check.
Step 2 — Build and maintain the “Current document list” (what is live)
- Add one line for each key document/drawing that could affect the work.
- Record the document reference exactly as issued (this prevents mix-ups).
- Use the title/area field to make it obvious (e.g., “Block A – Level 2 drainage”).
- Set a clear status:
- For construction = live and can be built to
- For review / draft = not live
- Superseded = replaced; should not be on the wall or in the workface pack
- As-built = record at completion
- Update the revision and issue date immediately when a new version arrives.
Practical rule: If it isn’t on the current list as “for construction”, don’t build to it.
Step 3 — Record “Where the controlled copy is kept” (so the team uses one version)
- For each key item, write the exact site location of the controlled copy (e.g., “Site office, red lever-arch folder”, “iPad in supervisor van”).
- Add the digital location (short, clear path). Keep it consistent so people can find it quickly.
- Record who issued it (designer/PC) and the date you verified on site that the controlled copy matches the register.
Site reality tip: If you allow multiple printed packs, you must control change-out. Otherwise, stick to one controlled pack plus view-only copies clearly marked “uncontrolled”.
Step 4 — Use the “Revision change log” every time something changes
- Log it the day you receive it: date received, doc ref, revision.
- Explain what changed in plain English: what a gang needs to do differently (not design wording).
- Choose how you briefed it: pre-start, toolbox talk, supervisor briefing, noticeboard/email.
- Write who was briefed: names where possible, or crew names (“Groundworks gang”, “M&E subcontractor”).
- Remove/replace old copies: take old sheets down, swap the pack, and note where superseded copies went (archive/file/bin).
- Get a check: someone competent confirms old copies are removed and signs/records the check date.
What counts as a “brief”? Anything that reliably reaches the people doing the work and can be evidenced. If the change affects safety or method, a face-to-face briefing is best.
Step 5 — Do the weekly coordination meeting quick check
- Ask: “Any new drawings/specs/RAMS/permits this week?” If yes, ensure they’re logged and controlled copies are updated.
- Confirm old copies are removed from cabins, work areas, vans, and noticeboards.
- Confirm subcontractors have been told about relevant changes.
- Record short actions: what needs doing, who will do it, and by when.
Timebox it: 5–10 minutes is usually enough if you keep the register tidy.
Review and sign-off (what to check and when to escalate)
- Weekly review: Site Manager (or Document Control Owner) reviews and dates the weekly check notes.
- Change log check: For any revision that affects method/safety/quality, a supervisor should confirm briefing was done and old copies removed.
- Escalate if:
- Status is unclear (not clearly “for construction”).
- Two different revisions are found in use.
- A subcontractor is working from their own unverified prints.
- A drawing/spec change impacts programme, cost, temporary works, or safety controls.
Simple escalation route: Stop that task → confirm latest revision with PC/designer → update register → brief affected crews → restart.
Recordkeeping (storage, version control, retention)
- Where to store: Keep one live copy in the agreed project folder (digital) and one controlled site copy (paper/digital device).
- Naming: Use a consistent file name, e.g.
ProjectName_SiteDocumentControlRegister_YYYY-MM-DD. - Version control: Don’t overwrite without trace. Save weekly updates as a new dated PDF or keep a tracked spreadsheet with a clear revision history.
- Evidence to keep with it: drawing transmittals/emails, briefing attendance sheets, photos of updated noticeboards (where used), and any instructions from the PC/designer.
- Retention: Keep for the project duration plus your normal close-out period. If you’re unsure, keep it with the H&S file and QA records for the job so it’s available for audits, disputes, or handover.
How often to update (quick rules)
- Immediately: when you receive a new revision or new document.
- Weekly minimum: review in the coordination meeting even if “nothing changed”. Record that you checked.
- Daily (busy jobs): if drawings are moving fast, do a short daily check for the key packs (critical drawings, RAMS, permits).
Common mistakes (and how to avoid them)
- Mistake: Register updated but the wall drawings / site pack not swapped.
Fix: Treat “update register + swap controlled copy + remove old prints” as one job. Don’t split it. - Mistake: Document ref written differently to the issued ref (hard to track).
Fix: Copy the reference from the transmittal/drawing title block. - Mistake: Status not recorded (people assume it’s live).
Fix: If status is unknown, mark it “for review” until confirmed. - Mistake: Briefings are done but not evidenced.
Fix: Use the change log every time; write names/crews and the method. - Mistake: Subcontractors use their own prints from last week.
Fix: Agree one controlled source. Tell subs: “Check the register before you start.” Spot check at the workface. - Mistake: Digital folder becomes a dumping ground.
Fix: Keep a single “LIVE / For Construction” folder and move superseded items to an “ARCHIVE / Superseded” folder.
Worked scenario (what it looks like on a real site)
Situation: On Tuesday, the engineer issues a revised foundation drawing (Rev C) changing rebar details at Gridline B. The groundworks gang is due to fix steel Wednesday morning.
- The Document Control Owner logs the new drawing in the Current document list as “For construction”, Rev C, with the new issue date.
- They update the controlled copy location entry: swap the paper drawing in the site office folder and update the tablet PDF in the LIVE folder.
- They complete the Revision change log: “Rebar laps increased at Gridline B; add extra links as shown.”
- They brief the groundworks supervisor at pre-start and note “Groundworks gang + steel fixers” in the “who briefed” field.
- They remove the Rev B drawing from the noticeboard and mark it “Superseded” before filing it in the archive.
- At the weekly meeting, they confirm the change was actioned and record “Spot check workface pack Thursday” as an action.
Result: The gang works to Rev C, the old Rev B print isn’t in circulation, and you have a clear audit trail showing the change was controlled and communicated.
Principal Contractor Support
Running a CDM Project as Principal Contractor?
Get the structure, advice, and documentation support you need to manage the role properly.
When you take on the Principal Contractor role, the responsibility for the Construction Phase Plan, site safety records, RAMS, and CDM compliance usually lands on the desk of a busy director or site manager.
CTC South West provides practical advisory support and structured systems that help you keep your documentation organised, your responsibilities clear, and your projects ready for client checks or audits.
Expert CDM support, site-ready documentation, and organised compliance records — all built around how construction projects actually run.
- Construction Phase Plans structured and ready for client review
- RAMS and project documentation tailored to your actual work
- Ongoing competent person support for Principal Contractors