How to Use This Resource: Temporary Works Register & Design Check Record (BS 5975 / CDM 2015)

Principal Contractor Advisory Support

Need a Competent Health & Safety Advisor for Your CDM Project?

Practical CDM support for Principal Contractors — advice, documentation, and structured systems to help you run organised, compliant projects.

If you’re managing the Principal Contractor role alongside running the job, we provide the expert guidance and support that keeps your Construction Phase Plan, RAMS, and site records properly organised and ready when clients or auditors ask to see them.

Experienced construction safety advisors supporting SME Principal Contractors across the UK.

Purpose and outcome

This resource helps you control every temporary works item on the job (propping, formwork/falsework, edge protection, excavation support, working platforms, etc.) from identification through to authorised use and authorised striking.

It is set up to match the practical intent of BS 5975-style temporary works control (clear roles, categories, design/check, hold points and permits) and to create clear CDM 2015 evidence that temporary works were planned, designed/checked, installed, inspected, and removed in a controlled way.

Good completion looks like:

  • Every temporary works item is listed on the Temporary Works Register with an owner (TWC/TWS), category and current status.
  • No item is installed until the design and check are complete (“No design, no install”).
  • Hold points are enforced: Permit/Authorisation to Load/Use and Permit/Authorisation to Dismantle/Strike are recorded where used.
  • Inspection dates (post-install, routine, event) are recorded and easy to audit.

Who uses it (clear roles)

Role What they do Typical on small jobs
Temporary Works Co-ordinator (TWC) Overall control: sets up the register, confirms design and check arrangements, controls drawing revisions, and issues/controls permits/authorisations at hold points. PM or site manager (must be competent and have time to run the process).
Temporary Works Supervisor (TWS) Day-to-day supervision: pre-start checks, post-install inspection, routine/event inspections, and close-out checks for striking. Working foreman or supervisor.
Designer / Supplier Produces the design (drawings, calcs, assumptions/limits, sequence, inspection requirements). Temporary works engineer, scaffold designer, formwork supplier, shoring provider.
Checker Checks the design is suitable, complete and buildable for the brief and conditions. Records acceptance/rejection and actions. Independent engineer or competent person not producing the original design (often driven by category).
Install team / Subcontractor Builds to the latest approved revision, reports any clash/difference, and does not change the arrangement without approval. Your operatives and specialist subcontractors.

Practical point: Small jobs still need role clarity. Even if one person wears two hats, the responsibilities must be explicit and recorded.

When to use it (project workflow triggers)

  • Job start / mobilisation: create the register, name TWC/TWS, set Rev 0, add known temporary works from drawings/methods/programme.
  • Before ordering / delivery: add each new item and agree who designs and who checks it (don’t wait until it’s on the lorry).
  • Before installation: confirm design/check complete and latest revision is issued to site (hold point).
  • Before loading/using: post-install inspection recorded and permit/authorisation to load/use issued (hold point).
  • During use: routine inspections at the set frequency, plus event inspections after rain/wind (where relevant), impact, modification, or load/sequence change.
  • Before striking: confirm permanent works can support itself and permit/authorisation to strike is issued (hold point).

Before you start (what you need ready)

For the Register

  • Project details and a simple register revision approach (Rev 0, Rev 1, etc.).
  • Initial list of temporary works items (site walk-round + drawings + subcontractor proposals).
  • Named TWC and TWS.

For each item’s Design Check Record

  • Design brief: location, purpose, loads, limits, constraints, sequence and hold points.
  • Design pack: drawings/sketches (with revision), calculations, manufacturer/supplier data, assumptions and limits.
  • Interfaces: adjacent structures, services, excavations, public protection, crane/plant loads if relevant.
  • Category/check route: the temporary works category used on your job and whether an independent check is required.

How to complete it (step-by-step)

1) Build and maintain the Temporary Works Register (job-wide)

  1. Enter job details, TWC/TWS, start date, and current revision.
  2. Add each temporary works item with a unique ref (TW-01, TW-02, etc.) and a clear “what & where”.
  3. Record category (Cat 0/1/2/3 or your system) and who is responsible for design and check.
  4. Record drawing/calc references (including revision) and keep the item status current (planned → designed → checked → installed → in use → struck/closed out).

2) Complete the Design Check Record (one per item)

  1. Write/confirm the design brief (loads, limits, sequence, ground/base assumptions, exclusion zones).
  2. Record the design author, date and revision, and the drawing/calc references.
  3. Capture assumptions/limits and interfaces (this is where failures usually start).
  4. Record inspection requirements (who/when/frequency and event triggers).
  5. Record the check outcome: Accepted, Accepted with comments, or Reject.
  6. Close out checker comments (attach marked-up drawings) before installation/use.
  7. Get the sign-offs recorded (TWC acceptance and Checker completion).

3) Control installation and use (with hold points)

  1. Pre-start check: latest revision on site, right kit, bases/ground OK, team briefed.
  2. Install to drawing: if it can’t be built as drawn, stop and escalate (treat changes as a design change).
  3. Post-install inspection: confirm it matches the design (spacing, bracing, fixings, stability, access).
  4. Permit/Authorisation to Load/Use: issue only after post-install inspection and any hold points are met.
  5. Routine + event inspections: record dates, findings, and actions. If anything changes, consider re-design/re-check.
  6. Permit/Authorisation to Strike: only when the permanent works can support itself and the strike method/sequence is briefed.
  7. Close out: record struck/closed out on the register and file the final evidence.

Review and approval (what “good” looks like before sign-off)

TWC checks before accepting for use

  • The design matches the brief and the real site conditions (especially ground/bearing, access, and interfaces).
  • Correct drawing revision is issued to site and older revisions are controlled.
  • Hold points are clear and will be enforced (no “informal go-ahead”).

Checker checks before completing the design check

  • Loads, stability, bases/foundations, fixings, bracing/ties and sequence are addressed.
  • Buildability is realistic for the site team and method.
  • Inspection requirements and limits are stated clearly enough to brief the team.

Escalation points (stop and get support)

  • Ground conditions differ from assumptions (soft spots, water, made ground, undermining).
  • The team proposes “small tweaks” (moving props, removing ties, changing spacing).
  • Loads/sequence change (bigger pours, earlier loading, added storage, different plant).
  • Damage, movement, missing components, or a near miss.

Keeping it up to date (how often to review/update)

  • Live on site: update the register as soon as an item is added, revised, installed, authorised for use, inspected, or struck.
  • Weekly minimum: TWC reviews the full register (what’s coming up, what’s awaiting design/check, what’s ready for permits, what can be struck).
  • After events/changes: update immediately and trigger re-check if required by the change or category.

Recordkeeping (storage, version control, retention)

Store it so you can prove control

  • Keep the live register in the project H&S folder (digital) and a printed copy on site if useful.
  • File evidence by temporary works reference number (TW-01 pack, TW-02 pack, etc.).

What to file with it (audit-ready)

  • Design brief, design drawings/calcs (with revision), and design check record.
  • Marked-up drawings/comments and close-out of actions.
  • Pre-start, post-install, routine and event inspections.
  • Permits/authorisations to load/use and to strike (if used on your job).
  • Photos where they help show compliance or key details.

Retention

Keep with your project records as evidence under CDM 2015 and to satisfy client/Principal Contractor requirements. Use your company retention rule (and keep longer if specified by the client or the risk profile).

Common mistakes (and how to avoid them)

  • Mistake: Not treating “simple” items as temporary works (a few props, a short trench support, a loading platform).
    Avoid: If it supports, holds back, stabilises, or prevents a fall—put it on the register and control it.
  • Mistake: No clear category/check route, so the checking level is guessed.
    Avoid: Record the category (or “N/A”) and agree the check approach up front.
  • Mistake: Wrong drawing revision on site.
    Avoid: TWC controls issue; pre-start check includes “latest revision present”.
  • Mistake: Permit/authorisation is assumed rather than recorded.
    Avoid: Use the Inspection & Permit record section to evidence the hold point decisions.
  • Mistake: Changes made without re-check (“we just added one more prop”).
    Avoid: Treat changes as a design change; record event inspection and re-design/re-check where needed.
  • Mistake: Striking early to return kit.
    Avoid: Permit/authorisation to strike only when permanent works are confirmed able to carry loads.

Worked scenario (quick, realistic)

Scenario: Extension with a knock-through and a boundary excavation.

  1. The supervisor identifies and registers:
    • TW-01: Propping to existing masonry during knock-through.
    • TW-02: Excavation support to footing trench at boundary.
  2. The TWC agrees design briefs (loads/limits/sequence and inspection triggers) and records who designs and checks, including category/check route.
  3. Designer issues drawings and calcs; checker completes the design check record (accepted/accepted with comments/reject) and actions are closed out.
  4. TWS completes pre-start and post-install inspections; TWC issues permit/authorisation to load/use before work continues under/around the temporary works.
  5. After heavy rain, an event inspection is recorded for TW-02. If conditions differ from assumptions, work stops and the design/check is revisited.
  6. When permanent works are complete (e.g., lintel installed and secured; concrete achieved required strength), TWC issues permit/authorisation to strike, the works are struck safely, and the register is closed out.

Principal Contractor Support

Running a CDM Project as Principal Contractor?

Get the structure, advice, and documentation support you need to manage the role properly.

When you take on the Principal Contractor role, the responsibility for the Construction Phase Plan, site safety records, RAMS, and CDM compliance usually lands on the desk of a busy director or site manager.

CTC South West provides practical advisory support and structured systems that help you keep your documentation organised, your responsibilities clear, and your projects ready for client checks or audits.

Expert CDM support, site-ready documentation, and organised compliance records — all built around how construction projects actually run.

  • Construction Phase Plans structured and ready for client review
  • RAMS and project documentation tailored to your actual work
  • Ongoing competent person support for Principal Contractors

Practical advice from experienced construction safety advisors — supporting SME Principal Contractors across the UK.