Risk Assessment and Method Statement Template for Ground Beams and Bases
This document should not be used until it has been thoroughly reviewed by a competent person.
| Company name: | |
| Project title: | |
| Location: | |
| Contract No: | |
| Author: | |
| Reviewed by: | |
| Date: | |
| Signature: |
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
Method Statement : Formwork to pile caps ground beams and bases
Explanation
Formwork to pile caps, ground beams, and bases involves the construction of temporary moulds into which concrete is poured to form the structural elements of a building or infrastructure project. This process requires the use of both proprietary shuttering systems and custom-made timber components to create precise shapes and dimensions as specified in the design plans. The primary aim of this task is to ensure that the concrete sets in the desired configuration, providing the necessary support and stability for the structure. Proper execution of formwork is critical to achieving structural integrity and safety, necessitating meticulous planning, skilled workmanship, and adherence to health and safety protocols.
Responsibilities
- Site Manager: Ensure all formwork activities are planned and executed in compliance with health and safety regulations.
- Formwork Supervisor: Oversee the installation and removal of formwork, ensuring adherence to safety procedures.
- Health and Safety Officer: Conduct regular inspections and risk assessments to identify and mitigate potential hazards.
- Formwork Carpenter: Assemble and dismantle formwork components safely, following the specified design and instructions.
- Crane Operator: Safely operate lifting equipment to position formwork materials as required.
- Labourer: Assist in the handling and positioning of formwork materials, ensuring safe manual handling practises.
- Engineer: Verify that formwork designs meet structural requirements and safety standards.
- First Aider: Provide immediate medical assistance in the event of an accident or injury on site.
Equipment
- Hammer
- Spirit level
- Tape measure
- Circular saw
- Power drill
- Wrench set
- Shovel
- Crowbar
- Clamps
- Concrete vibrator
- Hard hat
- Safety goggles
- High-visibility vest
- Steel-toe boots
- Gloves
- Hearing protection
- Dust mask
Operation
- Conduct a risk assessment to identify potential hazards and implement control measures.
- Ensure all personnel involved are trained and competent in formwork operations.
- Verify that all necessary permits and approvals are in place.
- Inspect the work area for any hazards, such as uneven ground or overhead obstructions.
- Ensure the work area is clear of debris and hazards, and verify that the ground is stable and level.
- Inspect all formwork materials, including proprietary shuttering and timber components, for defects or damage.
- Ensure all personnel are equipped with appropriate personal protective equipment (PPE).
- Begin assembling the formwork according to the design specifications, using appropriate tools and equipment.
- Install proprietary shuttering systems as per the manufacturer’s instructions.
- Assemble made-up timber components accurately to fit the design and secure them in place.
- Install adequate bracing and support to prevent movement or collapse of the formwork.
- Use spirit levels and measuring tools to ensure the formwork is correctly aligned and levelled.
- Conduct a thorough inspection of the assembled formwork for stability and compliance with design specifications.
- Establish safe access and egress routes for workers, ensuring clear pathways.
- Maintain clear communication among team members throughout the process.
- Continuously monitor the formwork during concrete pouring for signs of instability or failure.
- After concrete has been poured and set, inspect the formwork for any signs of distress or damage before removal.
- Carefully dismantle the formwork once the concrete has cured sufficiently, following a reverse order of assembly.
- Remove all formwork materials and debris from the site, ensuring it is left in a clean and safe condition.
Risk Assessment : Formwork to pile caps ground beams and bases
Working at Height : Low (1)
Who might be harmed: Construction workers | Site supervisors | Subcontractors
Type of harm: Broken Bones | Death | Head Injury | Multiple / Various Injury
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Labourers | Formwork carpenters Type of harm: Back / Spinal Injury | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Muscular Injury Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Engineers | Inspectors Type of harm: Broken Bones | Crush / Entrapment | Death | Head Injury | Multiple / Various Injury Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Engineers Type of harm: Amputation | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Death | Eye Damage | Head Injury | Multiple / Various Injury Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Burns | Dermatitis | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Electricians | Site supervisors | Equipment operators | Subcontractors Type of harm: Burns | Death | Electrocution Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Inspectors | Visitors to the site Type of harm: Back / Spinal Injury | Broken Bones | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury | Muscular Injury Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Permanent Hearing Damage Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Burns | Death | Smoke Inhalation Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Asphyxia | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling formwork and concrete materials | Labourers involved in mixing and pouring concrete | Nearby workers on the construction site Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling formwork | Site supervisors and managers | Nearby tradespeople or contractors Type of harm: Eye Damage Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling concrete materials | Formwork carpenters | Labourers involved in mixing or pouring concrete Type of harm: Dermatitis Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling formwork | Nearby tradespeople working in close proximity Type of harm: Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling formwork Type of harm: Eye Damage Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling formwork materials | Labourers assisting with formwork installation or removal Type of harm: Dermatitis Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling cement | Labourers mixing or pouring concrete | Site supervisors overseeing formwork activities Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling cement | Formwork installation crew | Labourers mixing or pouring cement Type of harm: Eye Damage Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling cement | Formwork carpenters | Labourers mixing or applying cement Type of harm: Burns | Dermatitis Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling formwork materials | Site supervisors overseeing the work | Nearby workers on the construction site Type of harm: Asphyxia | Death | Illness | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling formwork materials | Labourers involved in mixing or applying solvents Type of harm: Eye Damage Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers handling formwork materials | Labourers involved in mixing or applying solvents Type of harm: Dermatitis Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Formwork to pile caps, ground beams, and bases involves the construction of temporary moulds into which concrete is poured to form the structural elements of a building or infrastructure project. This process requires the use of both proprietary shuttering systems and custom-made timber components to create precise shapes and dimensions as specified in the design plans. The primary aim of this task is to ensure that the concrete sets in the desired configuration, providing the necessary support and stability for the structure. Proper execution of formwork is critical to achieving structural integrity and safety, necessitating meticulous planning, skilled workmanship, and adherence to health and safety protocols. The primary hazards associated with formwork to pile caps, ground beams, and bases include the risk of falls from height during installation and removal, which can result in serious injury. Manual handling of heavy formwork materials poses a risk of musculoskeletal injuries. There is a danger of structural collapse if the formwork is not properly supported or secured, leading to potential harm to workers. Workers may be struck by moving formwork components or tools, causing injury. Exposure to hazardous substances, such as chemicals used in formwork materials, can lead to skin irritation or respiratory issues. Electrical hazards are present when working near power lines or electrical equipment. Slips, trips, and falls are common due to wet or uneven surfaces in the work area. Prolonged exposure to noise from machinery or tools can result in hearing damage. Fire hazards exist due to the use of flammable materials in formwork construction. Inadequate ventilation in enclosed formwork spaces can lead to poor air quality and respiratory problems. This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
Manual Handling : Low (1)
Structural Collapse : Low (1)
Striking Against Objects : Low (1)
Exposure to Hazardous Substances : Low (1)
Electrical Hazards : Low (1)
Slips, Trips, and Falls : Low (1)
Noise Exposure : Low (1)
Fire Hazards : Low (1)
Inadequate Ventilation : Low (1)
COSHH Assessment : Formwork to pile caps ground beams and bases
Concrete dust
Concrete dust is not an intended substance for use; rather, it is a byproduct generated during the cutting, grinding, or drilling of concrete materials.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Formwork release agents
Formwork release agents are applied to formwork surfaces to facilitate the easy removal of the formwork from the cured concrete, preventing adhesion and ensuring a smooth finish.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Cement
Cement is used as a binding agent in concrete mixtures to provide structural integrity and stability to pile caps, ground beams, and bases.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Solvents
Solvents are utilised for the cleaning and maintenance of tools and equipment used in formwork operations.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Toolbox Talk : Formwork to pile caps ground beams and bases
Introduction
Hazards
Formwork to pile caps ground beams and bases : Rules
Formwork to pile caps ground beams and bases : Warnings
Induction Record
Company name:
Project title:
Location:
Contract No:
Subject:
Risk Assessment and Method Statement : Formwork to pile caps ground beams and bases
Tutor:
Date:
Signature:
Name
Comments
Signature
Date