Risk Assessment and Method Statement Template for Foundations
This document should not be used until it has been thoroughly reviewed by a competent person.
| Company name: | |
| Project title: | |
| Location: | |
| Contract No: | |
| Author: | |
| Reviewed by: | |
| Date: | |
| Signature: |
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
Method Statement : Initial Foundation Works
Explanation
Initial foundation works involve the preparation and construction of the foundational base for a structure, ensuring stability and support for subsequent building activities. This process typically includes site clearance, excavation to the required depth, installation of level pins for accurate measurement, and the erection of formwork to shape and support concrete until it gains sufficient strength. The primary aim of these tasks is to establish a solid and level foundation that meets design specifications and safety standards, providing a reliable base for the entire structure.
Responsibilities
- Site Manager : Ensure all safety protocols are implemented and adhered to throughout the foundation works.
- Site Supervisor : Oversee daily operations, ensuring compliance with health and safety regulations.
- Health and Safety Officer : Conduct regular inspections and risk assessments to identify and mitigate hazards.
- Excavator Operator : Operate machinery safely and report any equipment malfunctions immediately.
- Groundworker : Follow safe working practises during excavation and installation of formwork.
- Surveyor : Accurately set out level pins and ensure all measurements are precise.
- Formwork Carpenter : Construct and install formwork according to design specifications, ensuring stability and safety.
- Labourer : Assist with manual tasks while adhering to manual handling guidelines to prevent injury.
- First Aider : Provide immediate medical assistance in the event of an accident or injury on site.
Equipment
- Excavators
- Shovels
- Spirit levels
- Tape measures
- Laser levels
- Formwork panels
- Hammers
- Nails and screws
- Concrete mixers
- Wheelbarrows
- Hard hats
- High-visibility vests
- Safety boots
- Gloves
- Eye protection
- Hearing protection
- Dust masks
Operation
- Conduct a thorough risk assessment of the site.
- Obtain and review all necessary permits and approvals.
- Identify and mark the location of underground services.
- Ensure all personnel are trained and competent for their tasks.
- Inspect and verify the condition of all machinery and equipment.
- Set up appropriate barriers and signage to secure the work area.
- Conduct a pre-start safety briefing with all personnel involved.
- Verify that all underground services have been identified and marked.
- Use appropriate excavation equipment, ensuring operators are trained and competent.
- Maintain safe distances from the edge of the excavation to prevent collapse.
- Install trench supports or shoring as required to prevent excavation collapse.
- Mark the locations for level pins according to the project specifications.
- Use appropriate tools to install level pins, ensuring they are securely fixed and at the correct height.
- Verify the accuracy of level pins using suitable measuring equipment.
- Inspect formwork materials for damage or defects before use.
- Assemble formwork according to design specifications, ensuring stability and alignment.
- Secure formwork with appropriate bracing to prevent movement during concrete pouring.
- Ensure all personnel involved in concrete pouring are wearing appropriate personal protective equipment (PPE).
- Use machinery and equipment safely, ensuring operators are trained and competent.
- Monitor the concrete pour to ensure even distribution and avoid overloading formwork.
- Conduct a thorough inspection of the completed foundation work to ensure compliance with design specifications.
- Remove any temporary supports or bracing only after the concrete has adequately set and cured.
- Clear the site of any debris or equipment, maintaining a tidy and safe work environment.
- Record all relevant data and observations during the foundation works process.
- Report any incidents or near misses to the appropriate personnel for further investigation and action.
Risk Assessment : Initial Foundation Works
Excavation collapse : Low (1)
Who might be harmed: Construction workers | Site supervisors | Equipment operators
Type of harm: Asphyxia | Back / Spinal Injury | Broken Bones | Crush / Entrapment | Death | Drowning | Head Injury | Multiple / Various Injury
Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Visitors to the site | Delivery personnel | Inspectors or surveyors | Subcontractors Type of harm: Amputation | Back / Spinal Injury | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Death | Eye Damage | Head Injury | Multiple / Various Injury Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Utility workers Type of harm: Asphyxia | Burns | Death | Electrocution Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Labourers | Equipment operators Type of harm: Back / Spinal Injury | Broken Bones | Muscular Injury Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Subcontractors | Visitors to the site Type of harm: Back / Spinal Injury | Broken Bones | Cuts and Abrasions | Death | Head Injury | Muscular Injury Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Permanent Hearing Damage Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Nearby residents | Visitors to the site Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Machine operators | Site supervisors Type of harm: Amputation | Back / Spinal Injury | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Death | Electrocution | Eye Damage | Head Injury Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers operating vibrating tools | Machine operators Type of harm: HAVS / Vibration White Finger Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Equipment operators | Site supervisors Type of harm: Cold / Pneumonia | Heat Stroke / Exhaustion | Illness Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Nearby workers from other trades Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Eye Damage Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Labourers | Formwork installers Type of harm: Burns | Dermatitis Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Site supervisors | Nearby workers from other trades Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Labourers Type of harm: Eye Damage Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Labourers | Formwork installers Type of harm: Dermatitis Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Machine operators | Site supervisors | Nearby workers from other trades Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Asphyxia | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Equipment operators Type of harm: Eye Damage Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Construction workers | Machinery operators | Maintenance personnel Type of harm: Burns | Dermatitis Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Initial foundation works involve the preparation and construction of the foundational base for a structure, ensuring stability and support for subsequent building activities. This process typically includes site clearance, excavation to the required depth, installation of level pins for accurate measurement, and the erection of formwork to shape and support concrete until it gains sufficient strength. The primary aim of these tasks is to establish a solid and level foundation that meets design specifications and safety standards, providing a reliable base for the entire structure. Initial foundation works present several significant hazards that must be meticulously managed to ensure the safety of all personnel involved. Excavation collapse is a primary concern, posing a risk of entrapment or injury to workers within the trench. The potential for being struck by falling objects, such as tools or materials, is heightened during these activities. Contact with underground services, including electrical cables and gas lines, can lead to severe injury or service disruption. Manual handling injuries are prevalent due to the lifting and positioning of heavy materials. Slips, trips, and falls are common on uneven or unstable ground surfaces. Noise exposure from machinery can lead to hearing damage, while dust exposure may cause respiratory issues. Additionally, machinery and equipment hazards, such as moving parts and operational malfunctions, require vigilant attention to prevent accidents. This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
Struck by falling objects : Low (1)
Contact with underground services : Low (1)
Manual handling injuries : Low (1)
Slips, trips, and falls : Low (1)
Noise exposure : Low (1)
Dust exposure : Low (1)
Machinery and equipment hazards : Low (1)
Vibration exposure : Low (1)
Weather conditions : Low (1)
COSHH Assessment : Initial Foundation Works
Cement dust
Cement dust is generated during the handling and mixing of cement for concrete production in foundation works.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Silica dust
Silica dust is not intentionally used but is generated during activities such as cutting, grinding, or drilling concrete and other materials containing crystalline silica.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Diesel exhaust emissions
Diesel exhaust emissions are a by-product of operating diesel-powered machinery and equipment used during initial foundation works.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Toolbox Talk : Initial Foundation Works
Introduction
Hazards
Initial Foundation Works : Rules
Initial Foundation Works : Warnings
Induction Record
Company name:
Project title:
Location:
Contract No:
Subject:
Risk Assessment and Method Statement : Initial Foundation Works
Tutor:
Date:
Signature:
Name
Comments
Signature
Date