Risk Assessment and Method Statement Template for Fencing
This document should not be used until it has been thoroughly reviewed by a competent person.
| Company name: | |
| Project title: | |
| Location: | |
| Contract No: | |
| Author: | |
| Reviewed by: | |
| Date: | |
| Signature: |
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
RAMS : Fencing Works
Site Specific Instructions
-
Removal of Fencing
- Work Process: Dismantle existing fencing using appropriate tools. Ensure all components are removed and disposed of in accordance with site waste management protocols.
- Hazards: Manual handling injuries, sharp edges, potential for falling materials, and trip hazards from dismantled components.
-
Preparing for New Fence Work
- Work Process: Clear the area of debris and level the ground as necessary. Mark out the fence line and position for posts.
- Hazards: Slips, trips, and falls, underground services interference, and manual handling injuries.
-
Installing Close Board Fencing
- Work Process: Erect posts at marked positions, ensuring they are securely set in concrete. Attach horizontal rails and fix vertical boards.
- Hazards: Use of power tools, manual handling, working at height if required, and potential for splinters.
-
Installing Chain-Link Fencing
- Work Process: Install posts and tension wires. Unroll chain-link mesh and secure to posts and tension wires.
- Hazards: Manual handling, sharp edges on mesh, tensioning injuries, and use of hand tools.
-
Install Galvanised Palisade Fencing
- Work Process: Position and secure posts in concrete. Attach palisade pales to rails using anti-tamper fixings.
- Hazards: Manual handling, sharp edges, use of power tools, and potential for falling objects.
-
Installing Mesh Panel Fencing
- Work Process: Set posts in concrete at specified intervals. Secure mesh panels to posts using appropriate fixings.
- Hazards: Manual handling, sharp edges, use of power tools, and potential for panel instability during installation.
-
Installation of Heras Fencing
- Work Process: Position temporary fencing panels in place and secure with clips. Ensure stability with weighted feet or ground pins.
- Hazards: Manual handling, panel instability, and potential for unauthorised access if not secured properly.
-
Fire Alarm Systems (General)
- Work Process: Coordinate with relevant personnel to ensure safe isolation and installation procedures.
- Hazards: Electrical hazards, potential for false alarms, and disruption to existing systems.
-
Fire Alarm Loops Isolation
- Work Process: Identify and isolate specific loops as per system design. Ensure all isolations are clearly marked.
- Hazards: Electrical hazards, risk of system failure if not properly managed.
-
Hook Up and Extension of Existing Fire Alarm System
- Work Process: Connect new components to existing system ensuring compatibility. Test connections thoroughly.
- Hazards: Electrical hazards, potential for system malfunction, and incorrect wiring risks.
-
New Fire Alarm System Installation
- Work Process: Install new fire alarm components as per design specifications. Ensure all wiring is compliant with regulations.
- Hazards: Electrical hazards, incorrect installation risks, and potential for system failure.
-
Commissioning Fire Alarm System
- Work Process: Conduct thorough testing of the entire system to ensure functionality. Document all test results.
- Hazards: Electrical hazards, potential for false alarms during testing, and incomplete commissioning risks.
Site Specific Hazards
Manual handling : Low (1)
Who might be harmed: Construction workers
Type of harm: Back / Spinal Injury | Muscular Injury
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Slips, trips, and falls : Low (1) Who might be harmed: Construction workers | Site visitors | Subcontractors Type of harm: Back / Spinal Injury | Broken Bones | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury | Muscular Injury Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Working at height : Low (1) Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Broken Bones | Death | Head Injury | Multiple / Various Injury Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Use of power tools : Low (1) Who might be harmed: Construction workers | Site supervisors Type of harm: Amputation | Broken Bones | Burns | Cuts and Abrasions | Death | Electrocution | Eye Damage | HAVS / Vibration White Finger | Head Injury | Permanent Hearing Damage Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Noise exposure : Low (1) Who might be harmed: Construction workers | Site visitors Type of harm: Permanent Hearing Damage Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Striking underground services : Low (1) Who might be harmed: Site operatives | Subcontractors Type of harm: Burns | Death | Electrocution | Multiple / Various Injury Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Contact with sharp objects : Low (1) Who might be harmed: Construction workers Type of harm: Amputation | Cuts and Abrasions Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Vehicle movement on site : Low (1) Who might be harmed: Site workers | Delivery drivers | Pedestrians Type of harm: Crush / Entrapment | Death | Broken Bones | Head Injury Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Weather conditions : Low (1) Who might be harmed: Construction workers Type of harm: Cold / Pneumonia | Heat Stroke / Exhaustion | Illness Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Dust inhalation : Low (1) Who might be harmed: Construction workers | Site visitors Type of harm: Respiratory damage / Asthma / COPD Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
All personnel involved in the fencing works must possess the necessary qualifications and experience pertinent to the specific tasks they are assigned. Competence is to be verified through the following procedures: Verification of Qualifications: All operatives must hold a valid Construction Skills Certification Scheme (CSCS) card relevant to their role. For those involved in the installation of electrical components related to fire alarm systems, an appropriate electrical qualification is mandatory. Experience Assessment: Personnel must have demonstrable experience in the type of fencing being installed, whether it be close board, chain-link, galvanised palisade, mesh panel, or Heras fencing. This experience should be documented and reviewed prior to commencement of work. Task-Specific Training: Operatives must undergo task-specific training sessions that cover the safe removal and installation of various fencing types. This includes understanding the use of specialised tools and equipment required for each type of fencing. Supervision: A competent supervisor with extensive experience in fencing works must be present on-site at all times. The supervisor is responsible for ensuring that all personnel adhere to safety protocols and that work is carried out to the required standard. Toolbox Talks: Regular toolbox talks are to be conducted, focusing on the specific risks associated with each type of fencing work. These talks should also address any updates in procedures or safety measures. Continuous Assessment: Competence is to be continuously assessed throughout the project. Any personnel found lacking in competence or failing to adhere to safety standards will be subject to retraining or reassignment. By adhering to these procedures, the project ensures that all personnel are adequately prepared and competent to safely execute the fencing works. All personnel involved in the fencing works must attend a comprehensive site induction prior to commencing any tasks. This induction will cover the specific risks and safety measures associated with the various types of fencing installations, including close board, chain-link, galvanised palisade, mesh panel, and Heras fencing. The induction will include: Identification of Hazards: Detailed discussion on potential hazards such as manual handling risks, working at height, and proximity to existing services. Safe Work Practises: Instruction on the correct use of tools and equipment specific to each type of fencing, including post drivers, wire tensioners, and cutting tools. PPE Requirements: Emphasis on the mandatory use of personal protective equipment, such as gloves, safety boots, high-visibility clothing, and eye protection, tailored to the specific tasks. Emergency Procedures: Explanation of site-specific emergency protocols, including muster points and communication channels in case of an incident during fencing operations. Environmental Considerations: Guidance on minimising environmental impact, such as managing waste materials from old fencing removal and ensuring new installations do not disrupt local wildlife. Training sessions will be conducted for any specialised tasks, such as the installation of galvanised palisade fencing, which may require additional skills due to its weight and complexity. Refresher training will be provided periodically to ensure ongoing compliance and safety awareness. All personnel involved in the fencing works shall utilise the designated site entrance and exit points, which are clearly marked and maintained to ensure safe passage. Access routes must be kept clear of obstructions at all times to facilitate the movement of materials and personnel. Temporary fencing will be erected to delineate the work area, ensuring that only authorised personnel have access. This is crucial for maintaining site security and preventing unauthorised entry. The temporary fencing must be inspected daily to ensure its integrity and effectiveness. For the installation of close board, chain-link, galvanised palisade, mesh panel, and Heras fencing, specific access points will be established to allow for the efficient delivery and movement of materials. These access points must be planned to minimise disruption to ongoing site activities and ensure the safety of all workers. Egress routes must be clearly identified and kept free from debris and equipment. In the event of an emergency, these routes will serve as the primary means of evacuation. All workers must be briefed on these routes during site inductions. During the removal of existing fencing, care must be taken to ensure that access and egress are not compromised. Temporary barriers or signage should be used to redirect personnel safely around the work area. Fire alarm system works will require coordination with the fencing activities to ensure that access for emergency services is not impeded. Any changes to access routes due to these works must be communicated promptly to all site personnel. Regular inspections will be conducted to ensure compliance with these procedures, and any deviations must be reported immediately to the site supervisor for corrective action. All personnel involved in the fencing works shall have access to adequate welfare facilities throughout the duration of the project. Welfare units will be strategically positioned on-site to ensure convenience and accessibility for all workers. These units will include clean and well-maintained toilets, handwashing facilities with running water, and a rest area equipped with seating and tables. Drinking water will be provided and replenished regularly to ensure hydration, particularly during warmer weather conditions. Workers will be encouraged to take regular breaks to prevent fatigue, especially when engaging in physically demanding tasks such as the installation of close board and chain-link fencing. Changing facilities will be available for operatives to change into appropriate work attire, including personal protective equipment (PPE) specific to fencing activities. This will include gloves, safety boots, and high-visibility clothing. The site manager will ensure that all welfare facilities are maintained in a hygienic condition, with regular cleaning schedules in place. Waste disposal from welfare units will be managed efficiently to prevent any health hazards. In the event of adverse weather conditions, provisions will be made for temporary shelter to protect workers from extreme temperatures or precipitation, ensuring that work can continue safely and comfortably. All personnel involved in the fencing works must ensure that they are aware of and comply with the specific permit requirements for the project. Permits to Work are mandatory for any activities that may impact existing services or require isolation, particularly when working near fire alarm systems. Prior to commencing any fencing removal or installation, a Permit to Dig must be obtained to ensure that underground services are identified and protected. This is crucial to prevent accidental damage to utilities, which could pose significant safety risks. For tasks involving the installation of fencing near fire alarm systems, a Permit for Fire Alarm Isolation is required. This ensures that any necessary isolation of fire alarm loops is conducted safely and in coordination with the site’s fire safety officer. The permit must detail the specific zones affected and the duration of the isolation. In instances where fencing works may obstruct emergency access routes or exits, a Permit for Temporary Obstruction must be secured. This permit will outline alternative arrangements to maintain safe access and egress at all times. All permits must be reviewed and authorised by the site manager before work commences. It is imperative that copies of all relevant permits are kept on-site and accessible for inspection throughout the duration of the works. Compliance with these procedures is non-negotiable to ensure the safety and integrity of the site and its occupants. All tools and equipment utilised for the fencing works shall be inspected prior to use to ensure they are in good working condition. Defective tools must be immediately removed from service and reported to the site supervisor. Hand tools such as post hole diggers, spades, and hammers will be used for the removal and installation of fencing. These tools must be checked for damage, particularly handles and blades, to prevent injury during use. Power tools, including drills and saws, will be employed for cutting and securing fencing materials. Operators must be competent and trained in their use. Power tools must be fitted with appropriate guards and safety features, and any trailing cables should be managed to prevent trip hazards. For the installation of close board fencing, nail guns may be used. Only trained personnel are permitted to operate nail guns, and they must wear appropriate personal protective equipment (PPE) such as safety goggles and gloves. The use of concrete mixers may be required for setting fence posts. Operators must ensure that mixers are stable and positioned on level ground. All moving parts should be guarded, and PPE such as gloves and eye protection must be worn. Ladders may be necessary for reaching higher sections of fencing. Ladders must be inspected before use, correctly positioned, and secured to prevent slipping. Only one person should use a ladder at a time, maintaining three points of contact. All equipment must be stored securely when not in use to prevent unauthorised access or accidental damage. Regular maintenance checks should be documented, and any issues promptly addressed to ensure ongoing safety throughout the project. All existing underground and overhead services must be identified and clearly marked prior to the commencement of any fencing works. A comprehensive survey of the site should be conducted to ascertain the location of all utilities, including electrical, gas, water, and telecommunications. Isolation Procedures:
Electrical Services:
Gas and Water Services:
Telecommunications:
Fire Alarm Systems:
General Precautions:
All personnel involved in the fencing works must be made aware of the potential hazardous substances that may be encountered during the project. Creosote-treated timber and galvanised materials are of particular concern. Prior to commencing work, a COSHH assessment must be conducted for any hazardous substances identified. This assessment should include the identification of substances, potential health risks, and control measures to mitigate exposure. Personal Protective Equipment (PPE) such as gloves and masks must be worn when handling treated timber or galvanised materials to prevent skin contact and inhalation of dust or fumes. Ensure that all PPE is compliant with relevant standards and is inspected regularly for damage. During the removal of existing fencing, care must be taken to identify any lead-based paints or coatings. If such materials are present, they must be handled in accordance with specific lead safety procedures, including the use of appropriate PPE and containment measures to prevent environmental contamination. All hazardous substances must be stored in clearly labelled containers, away from direct sunlight and sources of ignition. Storage areas should be secure and access restricted to authorised personnel only. In the event of a spill or accidental release of a hazardous substance, immediate action must be taken to contain and clean up the spill using appropriate spill kits. All incidents must be reported to the site supervisor and documented in accordance with company procedures. Waste materials containing hazardous substances must be disposed of in accordance with local regulations. A licenced waste carrier should be engaged for the removal and disposal of such materials, ensuring that all necessary documentation is completed and retained for audit purposes. Regular toolbox talks should be conducted to reinforce awareness of hazardous substances and safe handling practises among all site personnel. All deliveries of fencing materials shall be scheduled to minimise disruption and ensure the safety of all personnel on site. Delivery vehicles must be directed to designated unloading areas, which are to be clearly marked and free from obstructions. Upon arrival, the site supervisor will oversee the unloading process to ensure compliance with safety protocols. All personnel involved in unloading must wear appropriate PPE, including high-visibility clothing, safety boots, and gloves. Manual handling of fencing materials should be minimised. Where possible, mechanical aids such as forklifts or pallet trucks should be utilised. Personnel must adhere to safe lifting techniques to prevent injury. Materials such as close board panels, chain-link rolls, and palisade components must be stored securely on level ground, away from pedestrian routes and protected from adverse weather conditions. Stacking should not exceed a height that compromises stability. For mesh panel fencing, ensure that panels are handled with care to avoid damage to the mesh. Similarly, galvanised palisade fencing components should be handled to prevent bending or warping. All waste materials generated during the installation process must be collected and disposed of in accordance with site waste management procedures. Regular checks will be conducted to ensure compliance with these procedures. In the event of any spillage or damage during delivery, immediate action must be taken to rectify the situation and report it to the site supervisor. All personnel involved in the fencing works must adhere to the following Personal Protective Equipment (PPE) requirements to ensure safety and compliance with health and safety regulations: Hard Hats: Mandatory at all times to protect against potential head injuries from falling objects or accidental impacts during the removal and installation of fencing. High-Visibility Clothing: Essential for all workers to ensure visibility, particularly when working near vehicular traffic or machinery during the delivery and handling of fencing materials. Safety Footwear: Steel-toe boots must be worn to protect feet from heavy objects, such as fence panels or posts, that may be dropped during handling and installation. Gloves: Cut-resistant gloves are required to protect hands from sharp edges and splinters when handling materials such as close board, chain-link, palisade, mesh panel, and Heras fencing. Eye Protection: Safety goggles must be worn when cutting or grinding metal components, such as those used in galvanised palisade fencing, to prevent eye injuries from flying debris. Hearing Protection: Ear defenders should be used when operating loud machinery or equipment, particularly during the installation of metal fencing where power tools may be employed. Dust Masks: Required when working in dusty conditions, especially during the removal of old fencing or preparation of ground surfaces for new installations. All PPE must be inspected prior to use to ensure it is in good condition and fit for purpose. Any damaged or defective equipment must be reported and replaced immediately. Compliance with these PPE requirements will be monitored throughout the project to maintain a safe working environment. In the event of an emergency during fencing works, all personnel must adhere to the following procedures: Immediate Response: Upon identifying an emergency, such as a structural collapse or injury, the nearest worker must alert others by shouting “Emergency” and, if safe to do so, activate the site alarm. Evacuation: All workers must cease operations immediately and proceed to the designated assembly point in an orderly manner, using the safest route available. Tools and equipment should be left in place unless they pose a hazard. First Aid: Trained first aiders on site should attend to any injured individuals promptly. First aid kits are located at the site office and with designated first aiders. Fire Safety: In case of fire, workers must not attempt to extinguish it unless trained and it is safe to do so. The priority is to evacuate and ensure all personnel are accounted for at the assembly point. Communication: The site manager or appointed safety officer will contact emergency services, providing details of the incident, location, and any injuries sustained. Isolation of Services: If the emergency involves utilities or services, such as electrical hazards during fencing installation, ensure that these are isolated immediately by qualified personnel. Re-entry Protocol: No one shall re-enter the site until it has been declared safe by the site manager or emergency services. Documentation: Following the incident, a detailed report must be completed by the site manager, including witness statements and any corrective actions taken to prevent recurrence. Review and Debrief: A debrief session will be conducted with all personnel involved to review the incident and improve future emergency response procedures. All workers must familiarise themselves with these procedures during site induction and regular safety briefings. Compliance is mandatory to ensure the safety of all personnel involved in fencing works. All fencing works shall be conducted with the utmost consideration for the safety of the public and occupiers. Clear signage will be erected around the perimeter of the work area to inform and warn individuals of ongoing activities. Barriers and fencing will be utilised to demarcate the work zone, ensuring that unauthorised personnel are kept at a safe distance. During the removal of existing fencing, temporary barriers will be installed to maintain site security and prevent public access. Access points for construction personnel will be clearly marked and controlled to prevent inadvertent entry by the public. For the installation of new fencing types, such as close board, chain-link, galvanised palisade, mesh panel, and Heras fencing, all materials will be securely stored within the site boundaries to prevent any risk of falling or being displaced into public areas. Work areas will be kept tidy and free from obstructions to minimise trip hazards. In areas where fire alarm systems are being worked on, appropriate measures will be taken to ensure that any necessary fire alarm loops isolation does not compromise the safety of building occupiers. Temporary fire safety measures will be implemented as required, and all personnel will be briefed on emergency procedures. Throughout the project, regular inspections will be conducted to ensure that all safety measures remain effective and that any potential risks to the public or occupiers are promptly addressed. Communication with nearby residents and businesses will be maintained to keep them informed of progress and any potential disruptions. All personnel involved in the fencing works must be vigilant for any materials suspected to contain asbestos, particularly when removing existing fencing or preparing groundworks. Prior to commencing any work, a thorough review of the asbestos survey report for the site must be conducted to identify any known asbestos-containing materials (ACMs) in proximity to the work area. If ACMs are identified or suspected during the removal of existing fencing, work must cease immediately, and the area should be cordoned off to prevent access. The discovery must be reported to the site manager and a competent asbestos contractor should be engaged to assess and manage the situation. Personnel must not attempt to handle or disturb any suspected ACMs. All workers must be briefed on the potential locations of ACMs and trained in recognising asbestos materials. Appropriate signage should be displayed to warn of the presence of asbestos in areas where it is known or suspected. During the installation of new fencing, care must be taken to avoid disturbing any ground or structures that may contain ACMs. If ground penetration is required, ensure that it is conducted in accordance with the guidance provided by the asbestos survey and any additional instructions from the asbestos contractor. All waste materials suspected of containing asbestos must be handled and disposed of in accordance with current regulations, ensuring that they are double-bagged and clearly labelled as hazardous waste. Documentation of disposal must be maintained for compliance purposes. Regular monitoring and inspections should be conducted throughout the project to ensure compliance with asbestos management procedures and to address any issues promptly. The monitoring of fencing works shall be conducted through regular site inspections and audits to ensure compliance with health and safety standards. Site supervisors will be responsible for conducting daily checks to verify that all fencing activities are being carried out in accordance with the approved method statement and risk assessments. Key monitoring activities include:
Daily Inspections: Supervisors will conduct daily visual inspections of the work area to ensure that all fencing materials and equipment are stored safely and that the site remains tidy and free from hazards. Compliance Checks: Regular checks will be made to ensure that all operatives are wearing the appropriate personal protective equipment (PPE) and adhering to safe working practises, particularly during the installation of different types of fencing such as close board, chain-link, and palisade. Tool and Equipment Monitoring: All tools and equipment used in the fencing works will be inspected before use each day to ensure they are in good working condition. Any defective tools or equipment will be removed from service immediately. Environmental Monitoring: Particular attention will be paid to ensuring that noise and dust levels are kept within acceptable limits, especially when removing existing fencing or installing new structures. Measures will be taken to minimise disturbance to nearby residents and businesses. Incident Reporting: Any incidents or near misses will be reported immediately to the site manager, who will conduct a thorough investigation and implement corrective actions as necessary. This will help prevent recurrence and improve overall safety performance. Weekly Audits: A formal audit will be conducted weekly by the health and safety advisor to review compliance with the method statement, assess the effectiveness of control measures, and identify any areas for improvement. All findings from monitoring activities will be documented, and any non-compliance issues will be addressed promptly to maintain a safe working environment throughout the duration of the fencing works. All waste generated from the fencing works shall be managed in accordance with the Waste Management Plan. Segregation of waste is paramount; materials such as old fencing panels, posts, and concrete footings must be separated at the source. Removal of fencing will result in waste that includes wood, metal, and concrete. These materials must be sorted into designated skips or containers on-site. Wooden fencing should be placed in the timber waste skip, while metal components such as chain-link and palisade fencing should be directed to the metal recycling skip. Concrete footings must be broken down and placed in a separate container for inert waste. For the installation of new fencing, packaging materials such as plastic wrap, cardboard, and metal banding must be collected and disposed of in the appropriate recycling bins. Any off-cuts or surplus materials should be assessed for potential reuse before being discarded. Heras fencing, being temporary, should be stored for reuse rather than disposed of. Damaged sections that cannot be reused must be recycled appropriately. All personnel involved in the fencing works must be briefed on the waste management procedures during site induction. Regular inspections will ensure compliance with these procedures, and any non-compliance will be addressed immediately. Documentation of waste transfer notes is required for all waste leaving the site, ensuring traceability and compliance with legal obligations. All personnel involved in the fencing works shall adhere to the following environmental procedures to minimise impact on the surrounding environment: Minimise Disturbance: Careful planning and execution of the removal and installation of fencing will be undertaken to minimise disturbance to local flora and fauna. Particular attention will be given to nesting birds and protected species, with work scheduled outside of sensitive periods where possible. Waste Management: All waste materials, including old fencing and packaging from new materials, shall be segregated and disposed of in accordance with site waste management protocols. Recycling opportunities will be maximised, particularly for metal components. Noise Control: Use of power tools and machinery will be restricted to designated working hours to reduce noise pollution. Equipment will be maintained in good working order to minimise noise emissions. Dust Suppression: Dust generation will be controlled by damping down surfaces during dry conditions, particularly when removing or installing fencing. This is crucial in areas close to residential properties or sensitive environments. Protection of Watercourses: Measures will be implemented to prevent any debris or contaminants from entering nearby watercourses during the works. This includes the use of silt fences or barriers where necessary. Material Storage: All materials, particularly those that could pose a risk to the environment, such as paints or preservatives used on fencing, will be stored securely and away from drainage systems to prevent accidental spillage. Vehicle Movements: Vehicle access routes will be clearly defined to prevent unnecessary damage to vegetation and soil compaction. Vehicles will be checked regularly for leaks to prevent contamination of the site. Lighting: Temporary lighting used during the works will be directed away from sensitive areas to minimise light pollution and disturbance to wildlife. By adhering to these procedures, the project aims to ensure that the environmental impact of the fencing works is kept to a minimum, aligning with best practises and regulatory requirements. The project team shall ensure that all fencing works are conducted with minimal disruption to near neighbours. Communication is paramount; therefore, prior to commencement, a letter drop will be conducted to inform neighbours of the schedule and nature of the works. Noise control measures will be implemented, including the use of low-noise equipment where feasible and restricting noisy operations to designated hours, typically between 08:00 and 17:00. Dust suppression techniques will be employed during the removal and installation of fencing, such as damping down surfaces and using dust extraction tools. Access routes for delivery vehicles will be planned to avoid residential areas where possible, and deliveries will be scheduled outside peak times to minimise traffic disruption. Site boundaries will be clearly marked and secured to prevent unauthorised access, ensuring the safety of both workers and the public. Temporary fencing, such as Heras panels, will be utilised to maintain site security and delineate work areas. Regular inspections will be conducted to ensure compliance with these procedures, and any complaints from neighbours will be addressed promptly by the site manager. All personnel involved in the fencing works must undergo a pre-start health assessment to ensure they are fit for the tasks at hand. This includes evaluating any pre-existing conditions that may be exacerbated by manual handling or prolonged outdoor work. Manual Handling: Workers must be trained in proper lifting techniques to prevent musculoskeletal injuries, particularly when handling heavy fencing materials such as close board panels and galvanised palisade sections. Mechanical aids should be used where possible to minimise manual handling. Noise Exposure: When using power tools for cutting or installing fencing, appropriate hearing protection must be worn to mitigate the risk of noise-induced hearing loss. Regular monitoring of noise levels should be conducted to ensure compliance with exposure limits. Vibration: Operatives using vibrating tools, such as post drivers, must adhere to safe usage times to prevent hand-arm vibration syndrome (HAVS). Tools should be regularly maintained to reduce vibration levels. Weather Conditions: Given the outdoor nature of fencing works, workers must be prepared for varying weather conditions. Adequate hydration, sun protection, and appropriate clothing for cold or wet weather are essential to prevent heat stress or hypothermia. Dust and Particulates: When cutting materials, dust masks or respirators must be worn to protect against inhalation of dust and particulates. Dust suppression methods, such as water damping, should be employed where feasible. Repetitive Strain Injuries: Tasks involving repetitive motions, such as nailing or screwing fence panels, should be rotated among workers to reduce the risk of repetitive strain injuries. Regular breaks should be scheduled to allow for rest and recovery. First Aid: A first aid kit must be readily available on site, and at least one team member should be trained in first aid procedures. Immediate access to medical assistance should be ensured in case of injury. All amendments to the method statement for fencing works must be documented and authorised prior to implementation. Any changes to the scope of work, sequence of tasks, or materials used in the fencing installation must be reviewed and approved by the site manager. This includes alterations to the removal, preparation, and installation processes for various types of fencing such as close board, chain-link, galvanised palisade, mesh panel, and Heras fencing. Authorisation Process:
Identify the Need for Change: Any team member who identifies a requirement for amendment must report it immediately to the site supervisor. Document the Proposed Amendment: The proposed change must be clearly documented, detailing the specific aspect of the fencing work it pertains to and the rationale behind the amendment. Review by Site Manager: The site manager will review the proposed amendment to assess its impact on safety, quality, and project timelines. Consultation with Health and Safety Advisor: If necessary, consult with the health and safety advisor to ensure compliance with relevant legislation and standards. Approval: The site manager must provide written approval before any changes are implemented. This approval must be recorded in the project documentation. Communication: Once approved, communicate the amendment to all relevant personnel involved in the fencing works. Ensure that all team members understand the changes and any new procedures or precautions required. Update Documentation: Amend the method statement and any associated risk assessments to reflect the approved changes. Ensure that all documentation is up-to-date and accessible on-site. Monitoring Compliance:
Regular site inspections will be conducted to ensure adherence to the amended procedures. Any deviations from the authorised method statement must be reported and rectified immediately. Cement dust is generated during the mixing and setting of concrete for securing fence posts in place. Inhalation : Low (1) Who might be harmed: Construction workers handling cement | Site supervisors and managers | Nearby workers on site Type of harm: Respiratory damage / Asthma / COPD Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Eye Contact : Low (1) Who might be harmed: Construction workers handling cement | Nearby workers on site Type of harm: Eye Damage Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Skin Contact : Low (1) Who might be harmed: Construction workers handling cement | Labourers mixing or applying cement Type of harm: Dermatitis Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Wood preservative is intended to protect timber fencing components from decay, insect infestation, and weathering, thereby extending their lifespan and maintaining structural integrity. Inhalation : Low (1) Who might be harmed: Construction workers handling wood preservatives | Site supervisors overseeing the works Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Eye Contact : Low (1) Who might be harmed: Construction workers handling wood preservatives | Site supervisors overseeing fencing works Type of harm: Eye Damage Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Skin Contact : Low (1) Who might be harmed: Construction workers handling treated wood Type of harm: Dermatitis Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Paints and coatings are intended to provide protective and aesthetic finishes to metal fencing, ensuring durability and resistance to environmental elements. Inhalation : Low (1) Who might be harmed: Construction workers applying paints and coatings | Nearby site personnel Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Asphyxia | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Eye Contact : Low (1) Who might be harmed: Construction workers applying paints and coatings Type of harm: Eye Damage Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Skin Contact : Low (1) Who might be harmed: Construction workers handling paints and coatings | Maintenance personnel involved in touch-up tasks Type of harm: Dermatitis Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Solvents are intended for use in cleaning and preparing surfaces prior to the application of paints or coatings during fencing works. Inhalation : Low (1) Who might be harmed: Construction workers handling solvents | Site supervisors overseeing the works Type of harm: Asphyxia | Death | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Eye Contact : Low (1) Who might be harmed: Construction workers handling solvents Type of harm: Eye Damage Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Skin Contact : Low (1) Who might be harmed: Construction workers handling solvents | Maintenance personnel involved in equipment cleaning Type of harm: Dermatitis Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
Procedures
Personnel and competence
Site inductions and training
Access and egress arrangements
Welfare
Special permits
Tools and equipment
Services and isolations
Hazardous substances
Deliveries and materials handling
PPE
Emergency procedures
Safety of public and occupiers
Asbestos
Monitoring
Waste management
Environmental considerations
Near neighbours and nuisance
Occupational health
Amendments and authorisation
Activities
Site preparation and assessment
Removal of existing fencing
Ground clearance and levelling
Marking out fence line and post positions
Digging post holes
Installing fence posts
Installing close board fencing panels
Installing chain-link fencing
Installing galvanised palisade fencing
Installing mesh panel fencing
Installing Heras temporary fencing
Securing and stabilising all fencing types
Final inspection and quality check
Hazardous Substances
Cement dust
Wood preservative
Paints and coatings
Solvents
Induction Record
Company name:
Project title:
Location:
Contract No:
Subject:
Method Statement : Fencing Works
Tutor:
Date:
Signature:
Name
Comments
Signature
Date