Method Statement : Installation of Steel Column Using Lifting Equipment
Explanation
The installation of a steel column using lifting equipment is a critical task that involves the precise positioning and securing of structural elements onto concrete floors or foundations. This process requires the use of cranes, hi-abs, or telehandlers to lift and manoeuvre the steel column into its designated position. The task also involves the installation of fixings to ensure the column is securely anchored. Access to elevated positions is facilitated by Mobile Elevating Work Platforms (MEWPs) to allow for safe and efficient handling and securing of the column. The primary aim of this operation is to ensure the steel column is installed accurately and safely, providing structural integrity and stability as part of the overall construction framework.
Responsibilities
- Site Manager: Ensure all safety protocols and procedures are adhered to and oversee the entire installation process.
- Crane Operator: Operate the crane safely and efficiently, ensuring the steel column is lifted and positioned correctly.
- Rigger: Attach lifting equipment to the steel column securely and guide its movement during lifting.
- Banksman/Signaller: Communicate with the crane operator to guide the safe movement of the steel column.
- MEWP Operator: Operate the Mobile Elevating Work Platform safely to provide access for workers at height.
- Installation Crew: Secure the steel column in place and install fixings as per the engineering specifications.
- Health and Safety Officer: Monitor compliance with health and safety regulations and conduct risk assessments.
Equipment
- Crane, Hi-ab, or Telehandler
- Mobile Elevating Work Platform (MEWP)
- Lifting slings and shackles
- Steel fixings and bolts
- Torque wrench
- Spirit level
- Hard hats
- High-visibility clothing
- Safety boots
- Gloves
- Safety harnesses
- Eye protection
Operation
- Conduct a thorough risk assessment to identify potential hazards and implement control measures.
- Ensure all personnel involved are trained and competent in the use of lifting equipment and installation procedures.
- Inspect lifting equipment, including cranes, hi-abs, telehandlers, and MEWPs, to confirm they are in good working condition and have valid certification.
- Verify that the steel column and all fixings are free from defects and suitable for installation.
- Establish a clear communication plan, including hand signals or radio communication, for coordination among the team.
- Secure the work area by setting up barriers and signage to prevent unauthorised access.
- Review weather conditions to ensure they are suitable for lifting operations, avoiding high winds or adverse weather.
- Confirm that the foundation or concrete floor is prepared and capable of supporting the steel column.
- Plan the lifting operation, including the positioning of equipment and personnel, to ensure safe and efficient execution.
- Ensure that personal protective equipment (PPE) is available and worn by all personnel involved in the task.
- Conduct a pre-lift meeting with all personnel involved to review the lifting plan, roles, and responsibilities.
- Position the lifting equipment on stable ground, ensuring it is level and secure.
- Attach the lifting slings or chains to the steel column, ensuring they are properly rated and secured.
- Use a tag line to control the movement of the steel column during lifting.
- Lift the steel column slowly and steadily, maintaining clear communication between the operator and signal person.
- Guide the steel column into position over the concrete floor or foundation using the MEWP for access if necessary.
- Lower the steel column carefully into place, ensuring it aligns correctly with the fixings.
- Secure the steel column using appropriate fixings, ensuring they are tightened to the specified torque.
- Conduct a final inspection to confirm that the steel column is securely installed and all equipment is removed from the area.
- Clear the work area of any debris or obstructions and ensure it is safe for other operations to continue.
Risk Assessment : Installation of Steel Column Using Lifting Equipment
Crushing Hazards : Low (1)
Who might be harmed: Construction Workers | Crane Operators | MEWP Operators | Site Supervisors
Type of harm: Amputation | Back / Spinal Injury | Broken Bones | Crush / Entrapment | Death | Head Injury | Multiple / Various Injury
Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | Crane, Hi-ab, or Telehandler Operators | MEWP Operators | Site Supervisors
Type of harm:
Broken Bones | Crush / Entrapment | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury
Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Riggers | Ground Workers | MEWP Operators | Nearby Construction Workers
Type of harm:
Broken Bones | Crush / Entrapment | Death | Head Injury | Multiple / Various Injury
Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Crane Operator | Ground Workers | MEWP Operators | Nearby Personnel
Type of harm:
Crush / Entrapment | Broken Bones | Death | Electrocution | Head Injury
Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Crane Operators | Rigging Crew | Ground Workers
Type of harm:
Broken Bones | Crush / Entrapment | Death | Multiple / Various Injury
Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | MEWP Operators | Site Supervisors
Type of harm:
Back / Spinal Injury | Broken Bones | Cuts and Abrasions | Death | Head Injury | Muscular Injury
Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | MEWP Operators | Site Supervisors
Type of harm:
Broken Bones | Death | Head Injury | Multiple / Various Injury
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rigging Crew | Installation Workers | MEWP Operators
Type of harm:
Amputation | Crush / Entrapment | Cuts and Abrasions
Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Crane Operators | MEWP Operators | Ground Workers | Installation Crew
Type of harm:
Burns | Death | Electrocution
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Crane Operators | MEWP Operators | Ground Workers | Installation Crew
Type of harm:
Cold / Pneumonia | Heat Stroke / Exhaustion
Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers involved in the installation process | Crane, hi-ab, or telehandler operators | MEWP operators
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD
Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers handling the installation. | Nearby workers or personnel in the vicinity.
Type of harm:
Eye Damage
Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers handling the concrete or working nearby.
Type of harm:
Dermatitis
Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Welders | Nearby workers
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD | Smoke Inhalation
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Welders | Nearby workers
Type of harm:
Eye Damage
Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Welders
Type of harm:
Burns | Dermatitis
Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Crane operators | Telehandler operators | Ground crew assisting with installation
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Asphyxia | Respiratory damage / Asthma / COPD | Smoke Inhalation
Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Ground workers
Type of harm:
Eye Damage
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Installation workers
Type of harm:
Burns | Dermatitis
Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
The installation of a steel column using lifting equipment is a critical task that involves the precise positioning and securing of structural elements onto concrete floors or foundations. This process requires the use of cranes, hi-abs, or telehandlers to lift and manoeuvre the steel column into its designated position. The task also involves the installation of fixings to ensure the column is securely anchored. Access to elevated positions is facilitated by Mobile Elevating Work Platforms (MEWPs) to allow for safe and efficient handling and securing of the column. The primary aim of this operation is to ensure the steel column is installed accurately and safely, providing structural integrity and stability as part of the overall construction framework. The installation of a steel column using lifting equipment presents several significant hazards. There is a risk of crushing or trapping injuries during the lifting and positioning of the column, particularly if the column swings or falls unexpectedly. The use of cranes, hi-abs, or telehandlers introduces potential dangers such as equipment malfunction, overloading, or operator error, which could lead to dropped loads or collisions. Working at height, often necessary for securing the column, poses additional risks of falls, especially when using Mobile Elevating Work Platforms (MEWPs) for access. Furthermore, the installation of fixings into concrete floors or foundations requires careful handling to prevent injuries from tools and equipment. The presence of other workers and objects in the vicinity increases the likelihood of collisions or impact injuries during the operation. This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
Falling Objects : Low (1)
Swinging Loads : Low (1)
Equipment Failure : Low (1)
Overloading : Low (1)
Slips, Trips, and Falls : Low (1)
Working at Height : Low (1)
Pinch Points : Low (1)
Electrical Hazards : Low (1)
Weather Conditions : Low (1)
COSHH Assessment : Installation of Steel Column Using Lifting Equipment
Concrete dust
Concrete dust is generated during the drilling process into the floor or foundations to install fixings for the steel column.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Welding fumes
Welding fumes may be generated if welding is required to secure the steel column in place during installation.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Engine exhaust emissions
Engine exhaust emissions are not intended for use but are a by-product of operating machinery such as cranes, hi-abs, or telehandlers during the installation of steel columns.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Toolbox Talk : Installation of Steel Column Using Lifting Equipment
Introduction
Hazards
Installation of Steel Column Using Lifting Equipment : Rules
Installation of Steel Column Using Lifting Equipment : Warnings
Induction Record
Company name:
Project title:
Location:
Contract No:
Subject:
Risk Assessment and Method Statement : Installation of Steel Column Using Lifting Equipment
Tutor:
Date:
Signature:
Name Comments Signature Date