Risk Assessment and Method Statement Template for Dry lining, Plastering & Tape Jointing
This document should not be used until it has been thoroughly reviewed by a competent person.
| Company name: | |
| Project title: | |
| Location: | |
| Contract No: | |
| Author: | |
| Reviewed by: | |
| Date: | |
| Signature: |
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
RAMS : Dry lining, Plastering & Tape Jointing
Site Specific Instructions
Work Process and Associated Hazards
Existing Dry Lining Removal
Delivery of Dry Lining Materials to Site
Installation of a Stud Wall/Partition
Removal of Stud Wall/Partition
Loading Out of Plasterboard
Dot and Dabbing
Installation of Plasterboard on Ceilings and Walls
Bulkhead Installation
Taping and Jointing
Fire Rated Beam and Column Encasement
Installation of Access Panels
Mixing Materials or Compounds
Use of Power Stirrer
Two Coat Plastering
Skim Plastering
Application of Jointing Compounds
Manual handling : Low (1) Who might be harmed: Construction workers | Delivery personnel | Subcontractors Type of harm: Back / Spinal Injury | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Muscular Injury Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Slips, trips, and falls : Low (1) Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Back / Spinal Injury | Broken Bones | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury | Muscular Injury Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Working at height : Low (1) Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Broken Bones | Death | Head Injury | Multiple / Various Injury Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Dust inhalation : Low (1) Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Noise exposure : Low (1) Who might be harmed: Construction workers | Site supervisors | Nearby tradespeople Type of harm: Permanent Hearing Damage Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Use of power tools : Low (1) Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Amputation | Broken Bones | Burns | Cuts and Abrasions | Death | Electrocution | Eye Damage | HAVS / Vibration White Finger | Head Injury | Permanent Hearing Damage Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Falling objects : Low (1) Who might be harmed: Construction workers | Site supervisors | Adjacent trades Type of harm: Broken Bones | Crush / Entrapment | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Sharp tools and materials : Low (1) Who might be harmed: Construction workers | Site supervisors | Subcontractors Type of harm: Cuts and Abrasions | Eye Damage Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Electrical hazards : Low (1) Who might be harmed: Construction workers | Electricians | Site supervisors | Subcontractors Type of harm: Burns | Death | Electrocution Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Fire risk : Low (1) Who might be harmed: Construction workers | Site visitors | Subcontractors Type of harm: Burns | Death | Smoke Inhalation Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
All personnel involved in dry lining, plastering, and tape jointing works must possess the necessary skills and qualifications to perform their tasks safely and efficiently. Competence is to be verified through the following procedures: Verification of Qualifications: All operatives must hold relevant qualifications, such as NVQ Level 2 in Plastering or equivalent, specific to dry lining and plastering activities. Copies of certificates must be provided prior to commencement of work. Experience Assessment: Personnel must have demonstrable experience in similar projects. A minimum of two years’ experience in dry lining, plastering, and tape jointing is required. This will be assessed through references and previous project records. Site Induction: All workers must attend a site-specific induction that includes detailed information on the specific risks associated with dry lining, plastering, and tape jointing activities. This induction will cover safe handling of materials, use of tools, and emergency procedures. Tool Competency: Operatives must demonstrate competence in the use of specific tools and equipment, such as power stirrers and plasterboard lifters. Practical assessments will be conducted on-site to ensure proficiency. Ongoing Training: Continuous professional development is encouraged. Personnel will be provided with opportunities for further training in advanced techniques and safety practises related to dry lining and plastering. Supervision: A competent supervisor with extensive experience in dry lining and plastering will oversee all activities. The supervisor is responsible for ensuring that all work is carried out in accordance with the method statement and risk assessments. Regular Briefings: Daily briefings will be conducted to discuss specific tasks, potential hazards, and control measures. Attendance is mandatory for all personnel involved in the day’s activities. By adhering to these procedures, the project ensures that all personnel are adequately prepared and competent to undertake dry lining, plastering, and tape jointing works safely and effectively. All personnel involved in the dry lining, plastering, and tape jointing works must attend a site-specific induction prior to commencing any activities. This induction will cover the unique risks and safety measures associated with these tasks. The induction will include: Identification of Hazards: Specific hazards related to dry lining, plastering, and tape jointing, such as dust exposure, manual handling risks, and working at height, will be highlighted. Safe Work Practises: Detailed instructions on safe handling and installation of materials, including the correct use of tools and equipment like power stirrers and plasterboard lifters. Emergency Procedures: Clear guidance on emergency protocols specific to the work area, including evacuation routes and muster points relevant to the locations where dry lining and plastering are being conducted. PPE Requirements: Emphasis on the mandatory use of appropriate personal protective equipment, such as dust masks, safety goggles, and gloves, tailored to the specific tasks of plastering and jointing. Training Verification: Verification of relevant training certifications for operatives, particularly those using specialised equipment or performing tasks such as fire-rated encasement installations. Environmental Considerations: Instructions on managing waste materials from plastering activities and minimising dust emissions during mixing and application processes. Attendance at the induction will be recorded, and only those who have completed it will be authorised to work on the dry lining, plastering, and tape jointing tasks. Regular refresher sessions will be conducted to ensure ongoing compliance and awareness. Access to the work areas for dry lining, plastering, and tape jointing shall be strictly controlled to ensure safety and efficiency. All personnel must use designated access routes to prevent interference with other site operations and maintain a clear path for emergency egress. Scaffold towers or mobile elevated work platforms (MEWPs) will be utilised for tasks involving ceilings or high walls. These must be inspected daily before use, and only trained operatives are permitted to operate them. Ladders may be used for short-duration tasks, provided they are secured and used in accordance with the manufacturer’s instructions. Loading and unloading of materials such as plasterboards must occur at designated drop-off points. These points should be as close as possible to the work area to minimise manual handling risks. Clear signage will be displayed to direct delivery vehicles and personnel to these points. Fire exits and escape routes must remain unobstructed at all times. Temporary barriers or signage will be employed to delineate work zones, ensuring that pathways remain clear for both workers and emergency services. In areas where bulkhead installations or fire-rated encasements are being constructed, temporary access solutions such as platforms or step-ups may be required. These must be stable, secure, and inspected regularly. All operatives must be briefed on the site-specific access arrangements during the induction process, with regular updates provided as necessary. Compliance with these procedures is mandatory to ensure a safe working environment for all involved in the dry lining, plastering, and tape jointing activities. All personnel involved in the dry lining, plastering, and tape jointing works shall have access to adequate welfare facilities in accordance with the Construction (Design and Management) Regulations 2015. Welfare provisions must be maintained to ensure the health and well-being of all operatives. Rest areas shall be provided with suitable seating and tables, ensuring a clean environment for breaks. These areas must be kept free from dust and debris associated with plastering activities. Handwashing facilities must be available, equipped with running water, soap, and towels, to remove any plaster or jointing compounds from the skin. Toilet facilities should be located within a reasonable distance from the work area, ensuring they are clean and stocked with necessary supplies. Given the nature of the work, changing facilities should be available for operatives to change out of work clothing that may become soiled with plaster or dust. Drinking water must be readily accessible to all workers to prevent dehydration, particularly when working in enclosed spaces where dust levels may rise. Additionally, first aid provisions must be in place, with a suitably stocked first aid kit and trained personnel available to address any injuries related to manual handling or tool use. Regular inspections of welfare facilities should be conducted to ensure compliance and address any issues promptly. All personnel involved in dry lining, plastering, and tape jointing works must ensure compliance with the following project-specific procedures regarding special permits: Permit to Work: Prior to commencing any work involving the installation or removal of stud walls/partitions, a Permit to Work must be obtained. This ensures that all necessary safety checks and authorisations are in place, particularly when working in areas with restricted access or where structural integrity may be affected. Hot Works Permit: If any task requires the use of equipment that generates heat, such as power stirrers or other electrical tools, a Hot Works Permit must be secured. This is crucial when working in environments where flammable materials are present or where fire-rated beam and column encasements are being installed. Confined Space Permit: In instances where dry lining or plastering activities occur within confined spaces, such as bulkhead installations or ceiling work in restricted areas, a Confined Space Permit is mandatory. This ensures that appropriate ventilation and emergency procedures are established. Access Equipment Permit: When using scaffolding, mobile elevated work platforms (MEWPs), or ladders for tasks such as ceiling plasterboard installation or high-level taping and jointing, an Access Equipment Permit must be obtained. This guarantees that all equipment is inspected and deemed safe for use. Environmental Permit: For projects involving significant waste generation from plasterboard offcuts or mixing compounds, an Environmental Permit may be required to manage disposal and minimise environmental impact. All permits must be reviewed and authorised by the site manager or designated safety officer before work commences. Compliance with these procedures is essential to maintain a safe working environment and adhere to legal requirements. All tools and equipment utilised for dry lining, plastering, and tape jointing must be inspected prior to use to ensure they are in good working condition. Defective tools must be removed from service immediately and reported to the site supervisor. Hand tools such as trowels, hawks, and jointing knives should be cleaned regularly to prevent material build-up, which could affect the quality of work and pose a safety risk. Power tools, including drills and power stirrers, must be operated by trained personnel only. Operators must ensure that all power tools are fitted with appropriate guards and safety devices. When using a power stirrer for mixing compounds, ensure that the equipment is stable and secure to prevent spillage or accidents. The operator must wear appropriate personal protective equipment (PPE), including eye protection and gloves, to safeguard against splashes. For the installation of plasterboard on ceilings and walls, lifting aids such as board lifters or trolleys should be used to minimise manual handling risks. Ensure that all lifting equipment is certified and inspected regularly. Scaffolding or mobile towers used for accessing higher areas must be erected by competent personnel and inspected before use. Ensure that all platforms are stable and free from obstructions. All electrical equipment must be 110V or battery-operated to comply with site safety standards. Regular PAT testing should be conducted to ensure electrical safety. Finally, ensure that all tools and equipment are stored securely when not in use to prevent unauthorised access or potential hazards on site. All electrical and mechanical services within the work area must be identified and clearly marked prior to the commencement of dry lining, plastering, and tape jointing activities. Isolation of services is mandatory where there is a risk of contact or interference during the works. Electrical Services:
Mechanical Services:
Communication:
Verification:
Reinstatement:
All personnel involved in dry lining, plastering, and tape jointing works must adhere to the following procedures regarding hazardous substances: Material Safety Data Sheets (MSDS): Prior to commencing work, all operatives must review the MSDS for each substance used, including plaster, jointing compounds, and adhesives. This ensures awareness of potential hazards and necessary precautions. Storage: Hazardous substances must be stored in designated areas, away from direct sunlight and sources of ignition. Ensure containers are sealed when not in use to prevent spills and contamination. Handling: When handling substances such as jointing compounds and plaster, operatives must wear appropriate personal protective equipment (PPE), including gloves and masks, to prevent skin contact and inhalation of dust. Mixing Procedures: Mixing of materials should be conducted in well-ventilated areas. Use mechanical mixers or power stirrers as per manufacturer instructions to minimise dust generation. Ensure that all equipment is checked for safety compliance before use. Spill Response: In the event of a spill, immediately contain the area using absorbent materials. Dispose of waste in accordance with site waste management protocols. Report any significant spills to the site manager promptly. Waste Disposal: All waste materials, including empty containers and excess compounds, must be disposed of in accordance with site-specific waste management procedures. Ensure that hazardous waste is segregated from general waste. Training: All operatives must receive training on the safe handling and use of hazardous substances specific to dry lining, plastering, and tape jointing tasks. Regular refresher courses should be conducted to maintain high safety standards. By adhering to these procedures, the risk associated with hazardous substances can be effectively managed, ensuring a safe working environment for all personnel involved in these construction activities. All deliveries of dry lining, plastering, and tape jointing materials shall be scheduled to minimise disruption and congestion on site. Delivery vehicles must adhere to designated routes and park in allocated areas to ensure safe unloading. Upon arrival, materials will be inspected for damage and verified against delivery notes. Any discrepancies or damages must be reported immediately to the site manager and supplier. Manual handling assessments will be conducted for all materials, with particular attention to the weight and size of plasterboards. Mechanical aids, such as trolleys or hoists, should be utilised wherever possible to reduce manual handling risks. Materials must be stored in a dry, secure area, protected from weather conditions. Plasterboards should be stacked flat on a level surface to prevent warping or damage. Compounds and plasters must be stored in accordance with manufacturer’s instructions, ensuring they are kept sealed until use. When moving materials to the work area, ensure clear access routes are maintained at all times. Loading out of plasterboard should be planned to coincide with installation schedules to avoid unnecessary handling and storage on site. Personnel involved in handling materials must wear appropriate personal protective equipment (PPE), including gloves and safety footwear, to mitigate risks associated with cuts, abrasions, and manual handling injuries. Regular toolbox talks will be conducted to reinforce safe handling practises and update workers on any changes to procedures or site conditions. All personnel involved in dry lining, plastering, and tape jointing works must adhere to the following Personal Protective Equipment (PPE) procedures: Head Protection: Hard hats must be worn at all times to protect against potential head injuries from falling objects or accidental impacts during the installation and removal of dry lining and stud walls. Eye Protection: Safety goggles or glasses are mandatory when cutting plasterboard, mixing materials, or using power stirrers to prevent dust and debris from causing eye injuries. Respiratory Protection: Dust masks or respirators must be worn during activities that generate dust, such as sanding, cutting plasterboard, and mixing compounds, to protect against inhalation of harmful particles. Hand Protection: Gloves should be worn to protect hands from cuts, abrasions, and chemical exposure when handling materials, applying jointing compounds, and during plastering tasks. Foot Protection: Steel-toed boots with slip-resistant soles are required to safeguard against foot injuries from heavy materials and to provide stability on potentially slippery surfaces. Hearing Protection: Ear defenders or earplugs should be used when operating power tools or in environments where noise levels exceed safe thresholds. Protective Clothing: Overalls or long-sleeved clothing should be worn to protect skin from irritants and to minimise contact with hazardous substances used in plastering and jointing processes. All PPE must be inspected regularly for damage and replaced as necessary to ensure continued protection. Compliance with these procedures is mandatory to maintain a safe working environment. In the event of an emergency during dry lining, plastering, and tape jointing activities, the following procedures must be adhered to: Immediate Response: Upon identifying an emergency, such as a fire or structural collapse, all operatives must cease work immediately and alert others in the vicinity by shouting “Emergency” and activating the nearest alarm. Evacuation Routes: All personnel must be familiar with the designated evacuation routes specific to the areas where dry lining and plastering works are being conducted. These routes should be kept clear of materials and equipment at all times. Assembly Points: Operatives must proceed to the pre-determined assembly point without delay. It is crucial that all workers involved in dry lining and plastering are accounted for at the assembly point. Fire Safety: Given the potential fire hazards associated with materials used in dry lining and plastering, such as plasterboard and jointing compounds, operatives must ensure that fire extinguishers are readily accessible and that they are trained in their use. First Aid: In case of injury, first aid kits must be available on-site, and trained first aiders should be notified immediately. Injuries related to manual handling or exposure to hazardous substances should be reported without delay. Communication: All workers must have access to a means of communication to contact emergency services if required. Mobile phones or site radios should be used to ensure prompt communication. Incident Reporting: Any incidents or near misses must be reported to the site manager as soon as possible after the emergency has been addressed. This will facilitate a review of procedures and implementation of corrective actions. Training and Drills: Regular emergency drills should be conducted to ensure all personnel are familiar with the procedures specific to dry lining, plastering, and tape jointing activities. Attendance at these drills is mandatory for all operatives. By adhering to these procedures, the safety of all personnel involved in dry lining, plastering, and tape jointing activities can be maintained during an emergency situation. The safety of the public and occupiers during dry lining, plastering, and tape jointing works is of paramount importance. The following procedures shall be strictly adhered to: Segregation: Erect physical barriers and signage to clearly demarcate work areas from public and occupier zones. Ensure that these barriers are robust and maintained throughout the duration of the works. Access Control: Implement controlled access points to prevent unauthorised entry into work areas. Only authorised personnel should be allowed entry, and a log of entries and exits should be maintained. Noise Management: Utilise noise-reducing tools and techniques where possible. Schedule particularly noisy activities, such as the use of power stirrers, during times that minimise disturbance to occupiers. Dust Control: Employ dust suppression methods, such as dust extraction systems and dampening surfaces, to minimise airborne particles. Ensure that all work areas are regularly cleaned to prevent dust accumulation. Material Storage: Store materials securely and away from public access routes. Ensure that materials are stacked safely to prevent collapse or obstruction. Communication: Maintain clear communication with occupiers regarding the schedule and nature of works. Provide advance notice of any activities that may impact their environment. Emergency Access: Ensure that emergency access routes are kept clear at all times. Regularly review and update emergency procedures in consultation with occupiers. Monitoring: Conduct regular inspections to ensure compliance with safety measures. Address any issues promptly to maintain a safe environment for both workers and occupiers. By adhering to these procedures, the safety of the public and occupiers can be effectively managed during the execution of dry lining, plastering, and tape jointing works. All personnel involved in dry lining, plastering, and tape jointing works must be vigilant for any materials suspected to contain asbestos. Prior to commencing any work, a thorough asbestos survey must be conducted by a competent person to identify any asbestos-containing materials (ACMs) within the work area. If ACMs are identified:
During the removal of existing dry lining:
For installation tasks such as stud walls, partitions, and plasterboard:
In case of accidental disturbance of ACMs:
All workers must be provided with appropriate asbestos awareness training and be familiar with the emergency procedures related to asbestos exposure. Regular monitoring and inspections should be conducted to ensure compliance with all safety protocols. The monitoring of dry lining, plastering, and tape jointing activities shall be conducted with a focus on ensuring compliance with health and safety standards, quality of workmanship, and adherence to the project schedule. Daily Inspections: The site supervisor shall conduct daily inspections of the work area to ensure that all safety measures are in place and that the work is being carried out in accordance with the method statement. Particular attention shall be paid to the condition and stability of erected partitions and the secure storage of materials. Quality Control Checks: Regular quality control checks shall be performed to verify that the installation of plasterboard, application of jointing compounds, and plastering meet the specified standards. Any defects or deviations from the specifications must be documented and rectified promptly. Environmental Monitoring: Dust levels shall be monitored continuously during sanding and mixing operations. Appropriate dust extraction systems and PPE must be utilised to minimise exposure. The effectiveness of these controls shall be reviewed regularly. Tool and Equipment Maintenance: All tools and equipment, including power stirrers, must be inspected before use to ensure they are in safe working condition. Any faults or issues identified must be reported immediately, and defective equipment must be taken out of service until repaired. Waste Management Audits: The disposal of waste materials, such as offcuts and packaging, shall be monitored to ensure compliance with waste management procedures. Segregation of waste streams must be maintained, and skips should be checked regularly for correct usage. Record Keeping: Detailed records of all monitoring activities, including inspection reports, quality control checklists, and maintenance logs, shall be maintained. These records will be reviewed during site audits to ensure ongoing compliance with health and safety requirements. All waste generated from dry lining, plastering, and tape jointing activities shall be managed in accordance with the following procedures: Segregation of Waste: Waste materials shall be segregated at the source into distinct categories, including plasterboard offcuts, packaging materials, and general construction debris. Plasterboard waste must be separated due to its potential for recycling. Designated Waste Areas: Clearly marked waste disposal areas shall be established on-site for each category of waste. These areas must be easily accessible to workers and regularly monitored to prevent overflow. Recycling of Plasterboard: Plasterboard offcuts and waste shall be collected in dedicated skips or containers for recycling. Coordination with a licenced recycling facility is required to ensure compliance with environmental regulations. Minimisation of Waste: Efforts shall be made to minimise waste generation by accurate measurement and cutting of materials, thereby reducing offcuts. Surplus materials should be returned to stock where feasible. Disposal of Hazardous Materials: Any hazardous substances, such as jointing compounds containing silica dust, must be disposed of in accordance with COSHH regulations. Appropriate containers and labels must be used to ensure safe handling and disposal. Documentation and Record Keeping: All waste transfers must be documented with waste transfer notes, detailing the type and quantity of waste, the date of transfer, and the destination. Records must be maintained for audit purposes. Training and Awareness: All personnel involved in dry lining, plastering, and tape jointing works shall receive training on waste management procedures, including the importance of segregation and recycling practises. Regular Inspections: Site management shall conduct regular inspections to ensure compliance with waste management procedures, addressing any issues promptly to maintain site cleanliness and environmental standards. By adhering to these procedures, the project aims to reduce environmental impact and promote sustainable construction practises. All personnel involved in dry lining, plastering, and tape jointing works shall adhere to the following environmental procedures to minimise impact: Dust Control: During the removal of existing dry lining and sanding of jointing compounds, dust extraction systems must be employed. Where feasible, wet methods should be used to suppress dust. All operatives must wear appropriate respiratory protective equipment (RPE) to prevent inhalation of airborne particles. Waste Management: Segregate waste materials such as plasterboard offcuts, packaging, and other debris at the source. Designated waste containers must be used for recyclable materials. Ensure that all waste is disposed of in accordance with local regulations and site-specific waste management plans. Noise Reduction: Utilise low-noise tools and equipment where possible, particularly during the installation and removal of stud walls and partitions. Operatives should be mindful of noise levels, especially when working near sensitive areas or during early morning and late evening hours. Material Storage: Store all dry lining materials, plasterboards, and compounds in a manner that prevents damage and contamination. Materials should be kept off the ground and covered to protect from adverse weather conditions. Spill Prevention: When mixing materials or compounds, ensure that spill kits are readily available. Any spills must be cleaned immediately to prevent contamination of the surrounding environment. Energy Efficiency: Use energy-efficient lighting and equipment during installation processes. Turn off equipment when not in use to conserve energy. Water Usage: Minimise water usage during mixing and cleaning processes. Reuse water where possible and ensure that any wastewater is disposed of in accordance with site-specific environmental guidelines. By adhering to these procedures, the project aims to reduce its environmental footprint while maintaining high standards of workmanship in dry lining, plastering, and tape jointing activities. To minimise disruption to near neighbours during dry lining, plastering, and tape jointing works, the following procedures shall be adhered to: Noise Control: All power tools, including power stirrers, shall be fitted with noise-reducing attachments where possible. Work involving high noise levels, such as the removal of existing dry lining or stud walls, shall be scheduled during agreed hours to avoid disturbance. Dust Management: Dust sheets and barriers shall be employed to contain dust within the work area. Vacuum extraction systems shall be used when cutting or sanding plasterboard. Regular cleaning of the site shall be conducted to prevent dust migration. Material Handling: Deliveries of dry lining materials and plasterboards shall be coordinated to avoid peak times and minimise traffic congestion. Loading and unloading activities shall be conducted swiftly and quietly. Communication: Prior to commencing works, a letter drop shall be conducted to inform neighbours of the nature and duration of the works. A contact number for the site manager shall be provided for any concerns or complaints. Waste Disposal: Waste materials, including plasterboard offcuts and packaging, shall be removed promptly and disposed of in designated skips to prevent unsightly accumulation. Lighting: Temporary lighting used for night work shall be directed away from neighbouring properties to prevent light pollution. By adhering to these procedures, the project aims to maintain a harmonious relationship with near neighbours and minimise any potential nuisance. To ensure the occupational health of all personnel involved in dry lining, plastering, and tape jointing works, the following procedures shall be strictly adhered to: Dust Control:
Manual Handling:
Use of Hazardous Substances:
Noise Exposure:
Ergonomics:
Skin Protection:
Training and Awareness:
All amendments to the method statement for dry lining, plastering, and tape jointing works must be authorised by the site manager prior to implementation. Any proposed changes should be documented in writing and submitted for review. The following procedures must be adhered to: Identification of Change: Any team member identifying a need for amendment must immediately report it to the site supervisor. This includes changes in materials, techniques, or sequence of tasks. Documentation: The proposed amendment must be clearly documented, detailing the nature of the change, the reason for the change, and any potential impacts on safety or quality. Review and Approval: The site manager will review the proposed amendment in consultation with the health and safety advisor. The review will focus on ensuring that the change does not compromise safety standards or project specifications. Communication: Once approved, the amendment will be communicated to all relevant personnel. This includes a briefing session to ensure that all team members understand the new procedures and any additional safety measures required. Record Keeping: All amendments and authorisations must be recorded in the project logbook. This record should include the date of the amendment, details of the change, and signatures of those authorising and acknowledging the change. Monitoring: Post-implementation, the site supervisor will monitor the amended procedures to ensure compliance and effectiveness. Any issues arising from the change must be reported immediately for further review. By adhering to these procedures, the project team ensures that all dry lining, plastering, and tape jointing activities are conducted safely and efficiently, maintaining compliance with health and safety regulations. Plaster dust is generated during the mixing and sanding of plaster, which is used to create a smooth, even surface on walls and ceilings prior to decoration. Inhalation : Low (1) Who might be harmed: Construction workers directly involved in plastering tasks | Other tradespeople working in close proximity Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Eye Contact : Low (1) Who might be harmed: Construction workers performing dry lining, plastering, and tape jointing | Other tradespeople working in close proximity Type of harm: Eye Damage Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Skin Contact : Low (1) Who might be harmed: Construction workers handling plaster materials | Dry lining and plastering operatives Type of harm: Dermatitis Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Silica dust is not intentionally used in dry lining, plastering, and tape jointing tasks; rather, it is a hazardous by-product generated during the cutting or sanding of materials such as concrete or brick. Inhalation : Low (1) Who might be harmed: Construction workers performing dry lining, plastering, and tape jointing | Other trades working in proximity Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Eye Contact : Low (1) Who might be harmed: Construction workers handling or cutting materials | Site supervisors overseeing dry lining and plastering tasks | Nearby tradespeople working in close proximity Type of harm: Eye Damage Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Jointing compound dust is generated during the sanding process of jointing compounds, which are applied to seams and joints in plasterboard to create a smooth, even surface for finishing. Inhalation : Low (1) Who might be harmed: Construction workers performing jointing tasks | Other trades working in close proximity | Cleaning staff on site Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Eye Contact : Low (1) Who might be harmed: Dry lining and plastering operatives | Other construction workers in proximity Type of harm: Eye Damage Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Skin Contact : Low (1) Who might be harmed: Construction workers handling jointing compounds Type of harm: Dermatitis Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Adhesives are utilised to securely bond plasterboard and other materials to various surfaces, ensuring stability and durability in construction applications. Inhalation : Low (1) Who might be harmed: Construction workers applying adhesives | Nearby tradespeople working in close proximity Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Asphyxia | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Eye Contact : Low (1) Who might be harmed: Construction workers applying adhesives Type of harm: Eye Damage Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Skin Contact : Low (1) Who might be harmed: Construction workers handling adhesives Type of harm: Dermatitis Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Solvents are utilised in adhesives and sealants to ensure proper bonding and finishing during the dry lining, plastering, and tape jointing processes. Inhalation : Low (1) Who might be harmed: Construction workers handling solvents | Site supervisors overseeing the work | Nearby tradespeople working in close proximity Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Asphyxia | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Eye Contact : Low (1) Who might be harmed: Construction workers handling solvents Type of harm: Eye Damage Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Skin Contact : Low (1) Who might be harmed: Dry lining and plastering operatives | Labourers handling materials Type of harm: Dermatitis Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
Site Specific Hazards
Procedures
Personnel and competence
Site inductions and training
Access and egress arrangements
Welfare
Special permits
Tools and equipment
Services and isolations
Hazardous substances
Deliveries and materials handling
PPE
Emergency procedures
Safety of public and occupiers
Asbestos
Monitoring
Waste management
Environmental considerations
Near neighbours and nuisance
Occupational health
Amendments and authorisation
Activities
Removal of existing dry lining
Delivery and unloading of dry lining materials
Installation of stud wall/partition
Removal of stud wall/partition
Loading out and positioning of plasterboard
Dot and dabbing application
Installation of plasterboard on ceilings
Installation of plasterboard on walls
Bulkhead installation
Taping and jointing of plasterboard
Fire-rated beam encasement
Fire-rated column encasement
Installation of access panels
Mixing of materials or compounds
Use of power stirrer for mixing
Application of two coat plastering
Skim plastering application
Application of jointing compounds
Hazardous Substances
Plaster dust
Silica dust
Jointing compound dust
Adhesives
Solvents
Induction Record
Company name:
Project title:
Location:
Contract No:
Subject:
Method Statement : Dry lining, Plastering & Tape Jointing
Tutor:
Date:
Signature:
Name
Comments
Signature
Date