Risk Assessment and Method Statement Template for Pre-Cast Concrete Works
This document should not be used until it has been thoroughly reviewed by a competent person.
| Company name: | |
| Project title: | |
| Location: | |
| Contract No: | |
| Author: | |
| Reviewed by: | |
| Date: | |
| Signature: |
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
RAMS : Pre-Cast Concrete Works
Site Specific Instructions
Pre-start Works The pre-start phase involves a thorough site inspection to ensure readiness for the pre-cast concrete works. This includes verifying that the ground conditions are stable and that all necessary permits and approvals are in place. Hazards associated with this phase include potential slips, trips, and falls due to uneven ground or debris. It is crucial to ensure that all personnel are equipped with appropriate personal protective equipment (PPE) such as hard hats, high-visibility vests, and safety boots. Delivery and Storage of Materials Materials must be delivered to the site in a manner that minimises disruption and ensures safety. The delivery area should be clearly marked and free from obstructions. Hazards during this phase include the risk of injury from moving vehicles and the potential for materials to fall during unloading. Proper lifting techniques and equipment must be employed to prevent musculoskeletal injuries. Materials should be stored on level ground, away from pedestrian routes, and secured to prevent movement. Installation of Block and Beam Floor The installation process requires precise coordination and adherence to the design specifications. Workers must be trained in the use of lifting equipment and the handling of pre-cast elements. Hazards include the risk of falling objects, which necessitates the use of exclusion zones beneath lifting operations. Additionally, there is a risk of falls from height when working on elevated structures; therefore, appropriate fall protection measures such as guardrails or harness systems must be implemented. It is essential to conduct regular inspections of lifting equipment to ensure it is in good working condition. Throughout all phases, effective communication among team members is vital to ensure safety and efficiency. Regular safety briefings should be conducted to reinforce awareness of potential hazards and the importance of adhering to safety protocols.
Who might be harmed:
Construction workers | Delivery personnel | Subcontractors
Type of harm:
Back / Spinal Injury | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Muscular Injury
Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers | Site supervisors | Subcontractors
Type of harm:
Back / Spinal Injury | Broken Bones | Death | Head Injury | Multiple / Various Injury
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Site operatives | Delivery drivers | Site supervisors | Subcontractors
Type of harm:
Back / Spinal Injury | Broken Bones | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury | Muscular Injury
Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers | Site supervisors | Delivery personnel
Type of harm:
Broken Bones | Crush / Entrapment | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury
Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers | Delivery personnel | Plant operators
Type of harm:
Amputation | Asphyxia | Back / Spinal Injury | Broken Bones | Crush / Entrapment | Death | Head Injury | Multiple / Various Injury
Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers | Site supervisors | Delivery personnel
Type of harm:
Permanent Hearing Damage
Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers | Site supervisors | Delivery personnel
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Site operatives | Crane operators | Banksmen
Type of harm:
Amputation | Back / Spinal Injury | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury | Muscular Injury
Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Site operatives | Delivery drivers | Pedestrians
Type of harm:
Amputation | Back / Spinal Injury | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury
Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
All personnel involved in the pre-cast concrete works must possess the necessary qualifications and experience relevant to their specific roles. Competency verification shall be conducted prior to commencement of the project, ensuring that all operatives hold valid Construction Skills Certification Scheme (CSCS) cards or equivalent. Site supervisors must have demonstrable experience in managing pre-cast concrete installations and should hold a Site Management Safety Training Scheme (SMSTS) certificate. They are responsible for overseeing the work and ensuring compliance with health and safety regulations. Operatives engaged in the installation of block and beam floors must have prior experience with similar pre-cast concrete systems. They should be familiar with the handling and positioning of pre-cast elements, as well as the use of any specialised equipment required for the task. Training sessions will be conducted to address specific risks associated with pre-cast concrete works, such as manual handling of heavy components and working at height. Attendance is mandatory for all personnel involved in these tasks. Toolbox talks will be held regularly to reinforce safe working practises and address any emerging issues. These talks will focus on task-specific hazards and the correct use of personal protective equipment (PPE). Records of competence and training will be maintained on-site and made available for inspection. Any gaps in skills or knowledge identified during the project will be addressed through additional training or supervision as necessary. All personnel involved in the pre-cast concrete works must undergo a comprehensive site induction prior to commencing any activities. This induction will cover the specific risks and safety measures associated with the installation of pre-cast concrete elements, including block and beam floors. Key Points: Attendance: All operatives, supervisors, and visitors must attend the site induction. Attendance will be recorded, and individuals will be required to sign an induction register. Content: The induction will include detailed information on: Training Requirements: Personnel must have received appropriate training in: Verification: Competence will be verified through certification checks and practical assessments where necessary. Only those deemed competent will be permitted to undertake tasks related to pre-cast concrete works. Refresher Inductions: Regular refresher inductions will be conducted to ensure ongoing awareness of safety procedures and any changes in site conditions or work methods. Language and Communication: Inductions will be delivered in a language understood by all attendees. Translation services or materials will be provided if necessary to ensure comprehension. By adhering to these procedures, the project aims to maintain a high standard of safety and competence among all personnel involved in the pre-cast concrete works. Access to the site for pre-cast concrete works shall be strictly controlled to ensure safety and efficiency. Designated access routes will be established for personnel and vehicles, clearly marked and maintained free from obstructions at all times. These routes will be communicated to all site operatives during the site induction. Egress points will be strategically located to facilitate safe and rapid evacuation in case of an emergency. All egress routes must remain unobstructed and clearly signposted, with emergency lighting provided where necessary. Vehicle access for delivery of pre-cast concrete components will be coordinated to minimise disruption and ensure safe unloading. A banksman will be present to guide vehicles and ensure safe manoeuvring within the site confines. Pedestrian access will be segregated from vehicle routes wherever possible, with barriers or fencing used to delineate pathways. Personnel must use designated walkways and avoid crossing vehicle paths unless at marked crossing points. Temporary access platforms or scaffolding required for the installation of block and beam floors must be erected by competent personnel and inspected regularly. These structures must comply with relevant safety standards and be capable of supporting the loads imposed by the pre-cast elements. All personnel involved in the pre-cast concrete works must wear appropriate personal protective equipment (PPE), including high-visibility clothing, to enhance visibility when accessing or egressing the work area. Regular inspections of access and egress arrangements will be conducted to ensure compliance with safety protocols, and any issues identified will be addressed promptly to maintain a safe working environment. All personnel involved in the pre-cast concrete works shall have access to adequate welfare facilities, which must be maintained in a clean and hygienic condition throughout the duration of the project. Sanitary conveniences shall be provided on-site, including flushing toilets with handwashing facilities equipped with running water, soap, and means of drying hands. These facilities must be located within a reasonable distance from the work area to ensure ease of access during breaks. Rest areas shall be designated for workers to take breaks, consume meals, and shelter from adverse weather conditions. These areas must be equipped with seating and tables, and should be protected from dust and noise associated with the installation of block and beam floors. Drinking water must be readily available on-site, clearly marked, and easily accessible to all workers. It is imperative that the water supply is regularly checked to ensure it remains uncontaminated. Given the nature of pre-cast concrete works, changing facilities should be provided for workers to change into and out of work attire. These facilities must offer privacy and secure storage for personal belongings. First aid provisions must be in place, with a suitably stocked first aid kit available at all times. A trained first aider should be present on-site to address any minor injuries that may occur during the handling and installation of pre-cast concrete elements. Regular inspections of welfare facilities shall be conducted to ensure compliance with health and safety standards, and any deficiencies must be promptly addressed to maintain a safe and comfortable working environment for all personnel. All personnel involved in the pre-cast concrete works must ensure compliance with the special permit procedures. Permits to Work are mandatory for specific high-risk activities associated with the installation of pre-cast concrete elements, particularly when working at height or in confined spaces. Prior to commencing any pre-cast concrete installation, a Permit to Work must be obtained from the site manager. This permit will confirm that all necessary safety measures are in place and that the work can proceed safely. The permit must detail: Lifting Operations require a separate permit, ensuring that all lifting equipment and accessories are inspected and certified. The permit must include: For hot works associated with cutting or welding of reinforcement bars or other metal components, a Hot Work Permit is required. This must specify: All permits must be visibly displayed at the work site and reviewed daily to ensure ongoing compliance with safety requirements. Any changes to the work scope or conditions necessitate a re-evaluation and re-issuance of the relevant permits. All tools and equipment utilised in the pre-cast concrete works must be suitable for the task and maintained in accordance with the manufacturer’s instructions. Prior to commencement, a thorough inspection of all equipment is mandatory to ensure operational safety and compliance with relevant standards. Lifting Equipment: Only certified lifting equipment shall be used for handling pre-cast concrete elements. This includes cranes, hoists, and any associated lifting accessories. All lifting operations must be conducted by trained personnel, with a competent person overseeing the process to ensure adherence to the lifting plan. Power Tools: Power tools required for cutting or finishing pre-cast elements must be checked for electrical safety, ensuring that all cables and connections are intact and free from damage. Tools must be fitted with appropriate guards and safety features, and operators must be trained in their safe use. Hand Tools: Hand tools such as hammers, chisels, and trowels must be inspected for wear and damage before use. Any defective tools should be removed from service immediately. Operators must use tools in accordance with their intended purpose to prevent injury. Personal Protective Equipment (PPE): Operators must wear appropriate PPE when using tools and equipment, including hard hats, safety boots, gloves, and eye protection. Additional PPE may be required based on specific tasks or risk assessments. Storage and Maintenance: Tools and equipment must be stored securely when not in use to prevent unauthorised access or damage. Regular maintenance schedules should be adhered to, with records kept of all inspections and repairs. Emergency Procedures: In the event of equipment failure or an incident involving tools, work must cease immediately, and the situation assessed by a competent person. Emergency procedures should be followed as outlined in the project’s health and safety plan. All existing services within the vicinity of the pre-cast concrete works must be identified and clearly marked on site plans prior to commencement. A thorough survey shall be conducted to ascertain the location of underground and overhead services, ensuring that all personnel are aware of their presence. Isolation of services is critical to ensure safety during the installation of block and beam floors. Prior to any work, all relevant services, including electrical, gas, and water, must be isolated by competent personnel. Verification of isolation must be confirmed through appropriate testing methods before proceeding with any installation activities. Coordination with utility providers is essential to ensure that any necessary disconnections or adjustments are carried out safely and in accordance with regulatory requirements. All isolations must be documented, and a permit-to-work system should be implemented to manage these activities effectively. During the delivery and storage of materials, care must be taken to avoid any interference with existing services. Designated storage areas should be established away from service routes to prevent accidental damage. In the event of an emergency or unexpected service encounter, immediate cessation of work is required, and the situation must be reported to the site manager. A risk assessment should be conducted to determine the appropriate course of action before resuming work. Regular monitoring and inspection of service isolations should be conducted throughout the duration of the pre-cast concrete works to ensure ongoing compliance and safety. All personnel involved in the pre-cast concrete works must be made aware of the potential hazards associated with the substances used during the process. Material Safety Data Sheets (MSDS) for all hazardous substances, including concrete additives and curing agents, must be readily available on site. Prior to commencing work, a COSHH (Control of Substances Hazardous to Health) assessment must be conducted to identify and evaluate the risks associated with each substance. This assessment should inform the selection of appropriate control measures to mitigate exposure. Personal Protective Equipment (PPE), such as gloves, goggles, and respiratory protection, must be worn when handling or working near hazardous substances. It is imperative that PPE is checked for integrity before use and replaced if damaged. During the delivery and storage of materials, ensure that all containers are clearly labelled and stored in a designated area away from direct sunlight and sources of ignition. Spill kits must be available on site to address any accidental releases promptly. When mixing or applying concrete additives, ensure that the area is well-ventilated to prevent the accumulation of harmful vapours. Workers should be trained in safe handling techniques and emergency procedures in case of exposure. Regular inspections and monitoring should be conducted to ensure compliance with safety procedures and to identify any potential issues with hazardous substances. Any incidents or near misses involving hazardous substances must be reported immediately and investigated to prevent recurrence. All deliveries of pre-cast concrete components shall be scheduled to minimise disruption and ensure efficient handling. Delivery vehicles must be directed to the designated unloading area by a competent banksman. The site manager shall ensure that the delivery schedule is communicated to all relevant personnel to avoid congestion and ensure safety. Upon arrival, each delivery must be inspected for any signs of damage or defects. Any issues identified must be reported immediately to the site manager and the supplier. Only authorised personnel shall handle the pre-cast components, using appropriate lifting equipment such as cranes or forklifts, operated by certified operators. Storage of materials must be on firm, level ground, away from site traffic and protected from adverse weather conditions. Components should be stacked securely, with adequate spacing to prevent accidental movement or collapse. The stacking height must not exceed the manufacturer’s recommendations. During handling, all personnel involved must wear appropriate personal protective equipment (PPE), including hard hats, high-visibility clothing, and safety boots. Manual handling should be minimised; where unavoidable, it must be conducted in accordance with manual handling regulations, ensuring that loads are within safe limits and proper techniques are employed. Regular inspections of lifting equipment and storage areas must be conducted to ensure ongoing compliance with safety standards. Any deviations or hazards identified must be addressed promptly to maintain a safe working environment. All personnel involved in the pre-cast concrete works must adhere to the following Personal Protective Equipment (PPE) requirements: Hard Hats: Mandatory at all times to protect against potential head injuries from falling objects during the installation of block and beam floors. High-Visibility Clothing: Essential for all workers to ensure visibility during the delivery and storage of materials, particularly in areas with vehicular movement. Safety Footwear: Steel-toe boots must be worn to safeguard against foot injuries from heavy pre-cast elements and equipment. Gloves: Cut-resistant gloves are required when handling pre-cast concrete elements to prevent hand injuries. Eye Protection: Safety goggles must be worn during any cutting or grinding activities associated with pre-cast concrete to protect against dust and debris. Hearing Protection: Ear defenders should be used in areas where noise levels exceed 85 dB, particularly during the operation of heavy machinery. Dust Masks/Respirators: FFP3 masks are necessary when working in dusty environments, especially during the cutting of concrete elements, to prevent inhalation of harmful dust particles. Compliance with these PPE requirements will be monitored by the site supervisor, and any non-compliance will be addressed immediately to ensure the safety of all personnel involved in the pre-cast concrete works. In the event of an emergency during pre-cast concrete works, the following procedures must be adhered to: Immediate Response: Upon identifying an emergency, such as a structural failure or collapse during the installation of block and beam floors, all personnel must cease operations immediately. The site supervisor is to be notified without delay. Evacuation: Personnel must evacuate the area in an orderly manner, using designated escape routes. It is imperative that all workers are accounted for at the assembly point, which is located at a safe distance from the work area. First Aid: Trained first aiders should attend to any injured individuals promptly. First aid kits are strategically placed on-site, and their locations are known to all workers. Emergency Services: If required, the site supervisor will contact emergency services by dialling 999, providing clear details of the incident, including the nature of the emergency and any injuries sustained. Communication: The site supervisor will ensure that all workers are informed of the situation and any further instructions. Communication devices must be readily available to facilitate this process. Containment: In case of a hazardous material spill during delivery or storage, containment measures must be implemented immediately to prevent environmental contamination. Spill kits are available on-site for this purpose. Post-Incident Review: Once the situation is under control, a thorough investigation will be conducted to determine the cause of the emergency. Lessons learned will be documented and shared with all personnel to prevent recurrence. Documentation: All incidents must be recorded in the site logbook, detailing the nature of the emergency, actions taken, and any injuries or damages incurred. It is crucial that all personnel are familiar with these procedures and participate in regular emergency drills to ensure preparedness. The safety of the public and occupiers during pre-cast concrete works is of paramount importance. The following procedures shall be strictly adhered to: Site Perimeter and Access Control: The site perimeter shall be secured with appropriate fencing to prevent unauthorised access. Clear signage indicating the nature of the works and potential hazards must be displayed prominently at all access points. Delivery Coordination: Deliveries of pre-cast concrete elements shall be scheduled during off-peak hours to minimise disruption and risk to the public. A designated marshalling area shall be established to manage delivery vehicles, ensuring they do not obstruct public pathways or roadways. Material Storage: Pre-cast concrete components shall be stored securely within the site boundaries, away from public access areas. Storage areas must be clearly marked and monitored to prevent accidental displacement or collapse. Installation Safety Measures: During the installation of block and beam floors, exclusion zones must be established beneath and around the work area to protect the public from falling objects. These zones should be clearly demarcated with barriers and warning signs. Communication with Occupiers: Regular communication with nearby occupiers shall be maintained to inform them of the schedule and nature of works. Any potential disruptions or risks must be communicated in advance, with contact details provided for further inquiries. Dust and Noise Control: Measures shall be implemented to control dust and noise emissions during installation activities. This includes the use of dust suppression techniques and noise barriers where necessary, to minimise impact on the surrounding environment and its occupants. Emergency Procedures: In the event of an incident affecting public safety, emergency procedures must be enacted immediately. This includes alerting emergency services, securing the site, and providing first aid if required. All personnel must be familiar with these procedures through regular drills and training sessions. By adhering to these specific procedures, the safety of the public and occupiers can be effectively managed throughout the duration of the pre-cast concrete works. All personnel involved in the pre-cast concrete works must be vigilant for any materials suspected to contain asbestos. Prior to commencement, a thorough review of the asbestos survey report for the site is mandatory. This ensures that all team members are aware of any identified asbestos-containing materials (ACMs) within the vicinity of the work area. In the event of encountering suspected ACMs during the installation of block and beam floors, work must cease immediately. The area should be cordoned off to prevent access, and the discovery must be reported to the site manager without delay. The site manager will then engage a licenced asbestos contractor to assess and, if necessary, safely remove or encapsulate the material. All workers must be trained in asbestos awareness, ensuring they can identify potential ACMs and understand the procedures to follow upon discovery. This training is crucial to maintaining safety and compliance with regulations. Regular inspections of the work area should be conducted to ensure no disturbance of ACMs occurs during the delivery, storage, and installation phases. These inspections should be documented, and any findings must be addressed promptly. Personal protective equipment (PPE) appropriate for asbestos risk must be available on-site, including disposable overalls and respiratory protective equipment (RPE), to be used if there is any risk of exposure during emergency situations. Communication with all site personnel regarding the presence and management of asbestos is essential. This includes clear signage and briefings to ensure everyone is informed and aware of the procedures in place. The monitoring of pre-cast concrete works shall be conducted with a focus on ensuring compliance with health and safety standards, as well as the quality of installation. Daily inspections will be carried out by the site supervisor to verify that all activities align with the method statement and risk assessments. Key areas of focus include: Alignment and Level Checks: Regular checks will be performed to ensure that the block and beam floor components are installed correctly, maintaining the specified alignment and level. Any deviations must be rectified immediately. Load Bearing Capacity: Continuous monitoring of the load-bearing capacity of the installed elements is essential. This includes verifying that no excessive loads are placed on the structure during installation. Condition of Pre-Cast Elements: Each pre-cast component will be inspected upon delivery and prior to installation for any signs of damage or defects. Damaged elements must not be used and should be reported to the project manager. Stability and Support: The stability of temporary supports and props must be checked regularly to prevent any movement or collapse during the installation process. Environmental Conditions: Weather conditions will be monitored to ensure they are suitable for installation activities. Adverse weather may necessitate a halt in operations to maintain safety standards. All findings from these monitoring activities will be documented in a daily log, which will be reviewed by the project manager to ensure ongoing compliance and address any issues promptly. All waste generated from the pre-cast concrete works shall be managed in accordance with the following procedures to ensure compliance with relevant legislation and minimise environmental impact. Segregation and Identification Concrete Waste Management Packaging Materials Documentation and Record Keeping Training and Awareness Monitoring and Review All personnel involved in the pre-cast concrete works shall adhere to the following project-specific environmental procedures: Minimisation of Dust and Particulates: During the installation of block and beam floors, dust suppression techniques must be employed. This includes the use of water sprays or dust extraction systems to minimise airborne particulates. Regular monitoring of dust levels should be conducted to ensure compliance with environmental standards. Noise Control Measures: The delivery and installation processes can generate significant noise. To mitigate this, all machinery and equipment must be fitted with appropriate silencers and maintained in good working order. Work should be scheduled during designated hours to minimise disturbance to nearby residents and businesses. Waste Management: All waste materials, including packaging from pre-cast components, must be segregated and disposed of in accordance with site waste management protocols. Recyclable materials should be separated and sent to appropriate facilities. A designated area for waste collection should be established on-site. Spill Prevention and Response: During the delivery and storage of materials, measures must be in place to prevent spills of any hazardous substances, such as oils or lubricants used in machinery. Spill kits should be readily available, and personnel trained in their use to ensure prompt response to any incidents. Protection of Watercourses: Care must be taken to prevent any runoff from entering nearby watercourses during the pre-cast concrete works. Silt fences or other barriers should be installed where necessary to control sedimentation and protect local water quality. Energy Efficiency: Efforts should be made to reduce energy consumption during the installation process. This includes turning off machinery when not in use and utilising energy-efficient equipment where possible. Biodiversity Considerations: Any potential impacts on local flora and fauna must be assessed prior to commencement of works. Protective measures should be implemented to safeguard any identified sensitive habitats or species in proximity to the site. By adhering to these procedures, the project aims to minimise its environmental footprint while ensuring compliance with relevant legislation and standards. The pre-cast concrete works will be conducted with due consideration to the impact on near neighbours, ensuring minimal disruption and nuisance. Communication with neighbouring properties will be established prior to commencement, informing them of the schedule and nature of the works. Noise control measures will be implemented, including the use of noise-reducing equipment and limiting operations to designated working hours. The installation of block and beam floors will be scheduled to avoid early mornings and late evenings, thereby reducing potential disturbances. Dust suppression techniques will be employed during the handling and cutting of pre-cast elements. Water spraying or dust extraction systems will be utilised to minimise airborne particles, particularly during dry conditions. Traffic management plans will be in place to manage the delivery of materials, ensuring that vehicle movements are coordinated to prevent congestion and disturbance. Delivery times will be arranged to avoid peak traffic periods, and vehicles will be instructed to switch off engines when stationary to reduce noise and emissions. Regular monitoring of site activities will be conducted to ensure compliance with these procedures, and any complaints from neighbours will be addressed promptly and effectively. A designated contact person will be available to handle any concerns raised by the local community. The occupational health procedures for pre-cast concrete works are designed to mitigate risks associated with the handling, installation, and finishing of pre-cast concrete elements. Manual Handling: Personnel must be trained in proper manual handling techniques to prevent musculoskeletal injuries. Mechanical aids such as cranes or hoists should be utilised wherever possible to minimise manual lifting. Dust Control: Cutting or drilling of pre-cast concrete elements may generate dust containing respirable crystalline silica (RCS). To control exposure, wet cutting techniques should be employed, and appropriate dust extraction systems must be in place. Workers must wear suitable respiratory protective equipment (RPE) when necessary. Noise Exposure: The use of power tools and machinery during installation can result in high noise levels. Noise assessments should be conducted, and hearing protection must be provided to workers exposed to noise levels above the action values. Vibration: Tools and equipment that produce hand-arm vibration (HAV) should be assessed for risk. Workers should be trained on the safe use of such equipment, and exposure should be limited by implementing job rotation and ensuring regular breaks. Chemical Exposure: Any chemical agents used in the curing or finishing of pre-cast concrete must be assessed for health risks. Safety data sheets (SDS) should be reviewed, and appropriate personal protective equipment (PPE) must be provided to prevent skin contact or inhalation. Ergonomics: The installation process should be planned to minimise awkward postures and repetitive movements. Adjustable work platforms and ergonomic tools should be used to reduce strain on workers. Health Surveillance: Regular health surveillance should be conducted for workers exposed to significant risks, such as RCS or noise, to detect early signs of occupational illness and implement corrective measures promptly. All amendments to the method statement for pre-cast concrete works must be documented and authorised prior to implementation. Any proposed changes to the procedures, particularly those affecting the installation of block and beam floors, must be communicated to the project manager and health and safety advisor. Authorisation Process: Identification of Change: Any team member identifying a need for amendment must document the rationale, including potential impacts on safety, quality, and schedule. Submission for Review: The proposed amendment must be submitted to the project manager for initial review. This includes any changes in delivery schedules or storage arrangements that may affect site operations. Consultation with Health and Safety Advisor: The health and safety advisor will assess the implications of the proposed change on risk assessments and ensure compliance with relevant legislation. Approval: The project manager, in consultation with the health and safety advisor, will authorise the amendment if deemed safe and compliant. This authorisation must be documented in writing. Communication: Once approved, the amendment must be communicated to all relevant personnel, including site operatives involved in pre-cast concrete works. A briefing session should be conducted to ensure understanding of the new procedures. Documentation Update: The method statement and associated risk assessments must be updated to reflect the authorised changes. All documentation should be readily accessible on-site. Monitoring: Post-implementation, the amended procedures should be monitored to ensure they are effective and do not introduce unforeseen risks. Note: No unauthorised changes to the method statement are permitted. Non-compliance with this procedure will result in disciplinary action.
Who might be harmed:
Construction workers | Site supervisors
Type of harm:
Respiratory damage / Asthma / COPD
Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers handling pre-cast concrete | Site supervisors and managers
Type of harm:
Eye Damage
Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers handling cement | Labourers involved in mixing or pouring concrete
Type of harm:
Burns | Dermatitis
Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers handling pre-cast concrete | Site supervisors and managers | Nearby tradespeople
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers handling the compounds | Nearby trades working in close proximity
Type of harm:
Respiratory damage / Asthma / COPD
Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers handling the compounds | Site supervisors overseeing the works
Type of harm:
Eye Damage
Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers handling the compounds | Site supervisors overseeing the works
Type of harm:
Burns | Dermatitis
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.Site Specific Hazards
Manual handling : Low (1)
Working at height : Low (1)
Slips, trips, and falls : Low (1)
Falling objects : Low (1)
Crushing injuries : Low (1)
Noise exposure : Low (1)
Dust inhalation : Low (1)
Use of lifting equipment : Low (1)
Vehicle movement on site : Low (1)
Procedures
Personnel and competence
Site inductions and training
Access and egress arrangements
Welfare
Special permits
Tools and equipment
Services and isolations
Hazardous substances
Deliveries and materials handling
PPE
Emergency procedures
Safety of public and occupiers
Asbestos
Monitoring
Waste management
Waste materials shall be segregated at the source into designated categories, including concrete offcuts, packaging materials, and general waste. Clearly labelled skips or containers will be provided on-site for each waste type to facilitate proper segregation.
Concrete offcuts and any excess material shall be collected and stored in a designated area. These materials will be assessed for potential reuse or recycling. Where feasible, concrete waste shall be crushed and reused as aggregate on-site or transported to an authorised recycling facility.
Packaging materials, such as plastic wrapping and wooden pallets, shall be separated from other waste streams. Plastic materials will be compacted and sent for recycling, while wooden pallets will be returned to the supplier for reuse or disposed of through a licenced waste contractor.
A waste management log shall be maintained on-site, documenting the type and quantity of waste generated, along with details of disposal or recycling. Waste transfer notes and consignment notes will be retained for all waste removed from the site to ensure traceability and compliance with the Duty of Care regulations.
All personnel involved in the pre-cast concrete works will receive training on the specific waste management procedures. Regular toolbox talks will be conducted to reinforce the importance of proper waste segregation and handling practises.
The effectiveness of the waste management procedures will be monitored throughout the project. Regular inspections will be conducted to ensure compliance, and any non-conformances will be addressed promptly. A review of the waste management strategy will be undertaken at project completion to identify areas for improvement in future projects.Environmental considerations
Near neighbours and nuisance
Occupational health
Amendments and authorisation
Activities
Site Preparation and Setup
Delivery and Storage of Pre-Cast Elements
Inspection and Verification of Pre-Cast Components
Installation of Block and Beam Floor
Use of Lifting Equipment and Cranes
Alignment and Levelling of Pre-Cast Units
Securing and Fixing Pre-Cast Elements
Grouting and Joint Sealing
Quality Control and Inspection
Removal of Temporary Supports
Site Clean-Up and Waste Disposal
Final Inspection and Handover
Hazardous Substances
Cement dust
Cement dust is generated during the handling and mixing of cement for the preparation of concrete components.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Silica dust
Silica dust is not intentionally used but is generated during the cutting, grinding, or drilling of concrete materials.
Inhalation : Low (1)
Concrete curing compounds
Concrete curing compounds are utilised to retain moisture in freshly placed concrete, ensuring proper hydration and strength development.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Induction Record
Company name:
Project title:
Location:
Contract No:
Subject:
Method Statement : Pre-Cast Concrete Works
Tutor:
Date:
Signature:
Name Comments Signature Date