Risk Assessment and Method Statement Template for Rope Access Activities
This document should not be used until it has been thoroughly reviewed by a competent person.
| Company name: | |
| Project title: | |
| Location: | |
| Contract No: | |
| Author: | |
| Reviewed by: | |
| Date: | |
| Signature: |
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
RAMS : Rope Access Activities
Site Specific Instructions
Work Process and Associated Hazards for Rope Access Activities Work Site Set-up Associated Hazards: Shot/Grit Blasting of Substrate Associated Hazards: Bird Netting Installation Associated Hazards: Installation of Bird Spikes Associated Hazards:
Who might be harmed:
Rope access technicians | Ground workers
Type of harm:
Back / Spinal Injury | Broken Bones | Death | Head Injury | Multiple / Various Injury
Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Ground workers | Site visitors | Pedestrians near the site
Type of harm:
Amputation | Back / Spinal Injury | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Death | Eye Damage | Head Injury | Multiple / Various Injury
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians
Type of harm:
Asphyxia | Death
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Ground workers
Type of harm:
Falls from height | Broken Bones | Death | Electrocution | Head Injury
Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Ground personnel | Nearby workers on site
Type of harm:
Cold / Pneumonia | Death | Drowning | Head Injury | Heat Stroke / Exhaustion | Illness
Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Ground personnel | Other contractors on site
Type of harm:
Crush / Entrapment | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Ground support personnel
Type of harm:
Asphyxia | Crush / Entrapment | Death | Multiple / Various Injury
Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Site workers | Supervisors
Type of harm:
Falls from height | Equipment failure | Inadequate communication | Inadequate training or competence
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
All personnel involved in rope access activities must possess the requisite qualifications and experience to ensure safe and efficient execution of tasks. Each team member shall hold a valid IRATA (Industrial Rope Access Trade Association) certification, appropriate to the level of work being undertaken. The team leader must be certified at Level 3, demonstrating advanced competence in supervising rope access operations. Prior to commencement of work, a comprehensive briefing will be conducted by the team leader to review the specific tasks, potential hazards, and emergency procedures. This briefing will ensure that all personnel are fully aware of their roles and responsibilities. Continuous assessment of competence will be carried out throughout the project. The team leader will monitor performance and adherence to safety protocols, providing additional guidance or training as necessary. Any personnel found lacking in competence or failing to adhere to safety standards will be immediately removed from the site until further training is completed. Key Points: All personnel involved in rope access activities must undergo a comprehensive site induction prior to commencing work. This induction will cover the specific risks and safety measures associated with rope access tasks, including: Rope Access Techniques: Detailed instruction on the specific rope access techniques to be employed, ensuring all operatives are familiar with the methods and equipment to be used. Equipment Familiarisation: Training on the correct use, inspection, and maintenance of all rope access equipment, including harnesses, ropes, and safety devices. Emphasis will be placed on recognising equipment faults and the importance of regular checks. Emergency Procedures: Clear guidance on emergency protocols, including rescue procedures specific to rope access scenarios. Personnel must be aware of the location of rescue equipment and trained in its use. Communication Protocols: Instruction on effective communication methods while working at height, including hand signals and radio use, to ensure clear and concise communication between team members. Site-Specific Hazards: Identification and discussion of any site-specific hazards that may impact rope access activities, such as adverse weather conditions or proximity to other work areas. Competency Verification: Verification of each operative’s competency through certification checks, ensuring all personnel hold valid IRATA (Industrial Rope Access Trade Association) qualifications appropriate to their role. Attendance at the induction will be recorded, and only those who have completed the induction will be permitted to participate in rope access activities. Regular refresher sessions will be conducted to ensure ongoing compliance and safety awareness. All personnel involved in rope access activities must utilise designated access points to the work site, ensuring that these points are clearly marked and free from obstructions. Access routes must be inspected daily to confirm their safety and suitability for use. Prior to commencing any rope access work, a thorough inspection of all anchor points is mandatory. These anchor points must be certified and capable of supporting the required loads. Only trained and competent personnel are authorised to set up and verify these anchor points. Rope access technicians must employ a dual-rope system, consisting of a working line and a safety line, both of which must be independently anchored. The integrity of these ropes must be checked before each use, and any signs of wear or damage must result in immediate replacement. During operations, a clear exclusion zone must be established beneath the work area to prevent unauthorised access and protect individuals from potential falling objects. This zone should be clearly demarcated with appropriate signage and barriers. Egress procedures require that all personnel descend in a controlled manner, ensuring that all equipment is retrieved and secured upon completion of the task. In the event of an emergency, a pre-planned rescue procedure must be in place, with all team members briefed on their roles and responsibilities. Regular communication checks via radio or other reliable means must be conducted to ensure constant contact between team members, particularly when accessing or egressing the work site. All personnel involved in rope access activities shall have access to appropriate welfare facilities, which must be established prior to the commencement of work. These facilities shall include: Rest Areas: Designated rest areas must be provided, ensuring they are easily accessible from the rope access site. These areas should be sheltered and equipped with seating to allow operatives to take breaks comfortably. Sanitary Conveniences: Adequate toilet facilities must be available on or near the site. These facilities should be maintained in a clean and hygienic condition, with regular cleaning schedules in place. Washing Facilities: Suitable washing facilities must be provided, including running water, soap, and means of drying. These facilities should be located close to the work area to allow operatives to clean up after tasks such as shot/grit blasting. Drinking Water: Potable drinking water must be readily available to all operatives. Water stations should be positioned conveniently to ensure hydration is maintained throughout the work period. Changing Rooms and Storage: If required, changing rooms should be provided for operatives to change into their work attire. Secure storage must also be available for personal belongings and equipment not in use. First Aid: A first aid kit, appropriate for the nature of rope access activities, must be available on site. A trained first aider should be present at all times during operations. All welfare provisions must comply with the relevant health and safety regulations and be regularly inspected to ensure they remain fit for purpose throughout the duration of the project. All personnel involved in rope access activities must obtain a Permit to Work prior to commencing any task. This permit ensures that all safety measures are in place and that the work is authorised by the site manager. The following procedures must be adhered to: Permit Application: The rope access supervisor shall submit a detailed application for a Permit to Work, outlining the specific tasks, equipment, and personnel involved. This application must be submitted at least 24 hours before the planned commencement of work. Risk Assessment Review: The site manager will review the risk assessment associated with the rope access activities to ensure all potential hazards have been identified and mitigated. Any additional control measures required must be implemented before the permit is granted. Site Inspection: Prior to issuing the permit, a site inspection will be conducted to verify that all safety equipment, including anchor points and personal protective equipment (PPE), is in place and meets the required standards. Permit Issuance: Once all conditions are satisfied, the site manager will issue the Permit to Work, which must be prominently displayed at the work site throughout the duration of the rope access activities. Daily Briefing: A daily briefing must be conducted by the rope access supervisor to ensure all team members are aware of the permit conditions, emergency procedures, and any changes in site conditions. Permit Closure: Upon completion of the rope access activities, the supervisor must inform the site manager, who will conduct a final inspection to ensure the work area is safe and all equipment is removed. The permit will then be formally closed. Failure to comply with these procedures may result in the suspension of work activities and potential disciplinary action. All tools and equipment utilised during rope access activities must be inspected prior to use to ensure they are in good working condition. Only equipment certified for rope access work shall be employed, and all items must comply with relevant British Standards. Rope Access Equipment: Shot/Grit Blasting Equipment: Bird Netting and Spike Installation Tools: General Procedures: By adhering to these procedures, the safety of personnel engaged in rope access activities is prioritised, ensuring compliance with health and safety regulations. All personnel involved in rope access activities must ensure that any services in the vicinity of the work area are identified and assessed for potential hazards. Prior to commencing work, a thorough inspection of the site must be conducted to locate any overhead or underground services that may pose a risk during operations. Isolation Procedures: Identification: Clearly identify all services, including electrical, gas, and water, within the work area. Use site plans and service drawings to assist in this process. Communication: Communicate with the site manager and relevant utility providers to confirm the presence and status of services. Ensure all team members are informed of identified services. Isolation: Where possible, isolate services that may interfere with rope access activities. This includes de-energising electrical lines and securing gas and water supplies. Obtain necessary permits for isolation from the site manager or utility provider. Verification: Verify that all isolations have been successfully implemented before commencing work. Use lock-out/tag-out systems where applicable to prevent accidental re-energisation. Signage and Barriers: Erect appropriate signage and barriers around isolated services to prevent unauthorised access and ensure the safety of all personnel. Monitoring: Continuously monitor the work area for any changes in service status or new hazards that may arise during the course of the project. Reinstatement: Upon completion of rope access activities, coordinate with the site manager and utility providers to safely reinstate any isolated services. Ensure all lock-out/tag-out devices are removed by authorised personnel only. By adhering to these procedures, the safety of all personnel engaged in rope access activities will be maintained, and potential risks associated with services will be effectively managed. All personnel involved in rope access activities must be fully briefed on the specific hazardous substances they may encounter during the project, particularly during the shot/grit blasting of substrates. Material Safety Data Sheets (MSDS) for all substances must be reviewed and understood by the team. Prior to commencing work, a COSHH assessment must be conducted to identify potential risks associated with the use of blasting materials and any other chemicals involved in the process. This assessment should include control measures to mitigate exposure, such as the use of appropriate Personal Protective Equipment (PPE), including respirators, gloves, and protective clothing. During shot/grit blasting, ensure that containment measures are in place to prevent the spread of dust and debris. This may involve the use of tarpaulins or other barriers to contain the work area. Regular air monitoring should be conducted to ensure that dust levels remain within safe limits. For bird netting and spike installation, ensure that any adhesives or sealants used are non-toxic and suitable for use at height. Personnel must be trained in the safe handling and application of these substances, with particular attention paid to preventing spills or accidental contact with skin. All hazardous substances must be stored securely when not in use, in accordance with manufacturer guidelines and relevant legislation. Ensure that spill kits are readily available at the work site, and that all personnel are trained in their use. In the event of an accidental release or exposure, follow the emergency procedures outlined in the COSHH assessment, including immediate evacuation from the affected area and seeking medical attention if necessary. Report all incidents to the site supervisor without delay. All deliveries of equipment and materials for rope access activities shall be scheduled to minimise disruption and ensure safety. The designated delivery area must be clearly marked and free from obstructions. Delivery vehicles must adhere to site speed limits and follow the designated route to the unloading area. Upon arrival, all materials and equipment shall be inspected for damage and conformity with specifications. Any discrepancies must be reported immediately to the site supervisor. Only trained personnel are authorised to handle materials and equipment related to rope access activities. Materials such as bird netting, spikes, and blasting media must be securely stored in a designated area, ensuring they are protected from adverse weather conditions. Manual handling of materials should be minimised; mechanical aids such as hoists or winches should be utilised wherever possible to transport materials to elevated work areas. Rope access technicians must ensure that all equipment is securely attached to their harnesses or work positioning systems when transporting materials at height. Care must be taken to prevent any items from falling, and all tools and materials should be tethered appropriately. Regular checks must be conducted to ensure that all lifting equipment is in good working order and has been inspected in accordance with LOLER regulations. Communication between ground personnel and rope access technicians is crucial during the handling and transportation of materials to ensure coordination and safety. All personnel engaged in rope access activities must adhere to the following project-specific procedures regarding Personal Protective Equipment (PPE): Full Body Harness: Each operative must wear a full body harness that complies with BS EN 361 standards. The harness must be inspected before each use for any signs of wear or damage. It is imperative that the harness is correctly fitted and adjusted to ensure maximum safety. Helmet: A helmet with a chin strap, conforming to BS EN 12492, must be worn at all times to protect against head injuries. The chin strap must be fastened securely to prevent the helmet from dislodging during operations. Rope Access Lanyards: Use double lanyards with energy absorbers, compliant with BS EN 355, to provide fall arrest protection. These lanyards must be attached to the designated anchor points at all times when operatives are working at height. Gloves: Suitable gloves must be worn to protect hands from abrasions and to provide a secure grip on ropes and equipment. Gloves should be checked for integrity before use. Footwear: Operatives must wear safety boots with non-slip soles and steel toe caps, conforming to BS EN ISO 20345, to prevent foot injuries and ensure stability on various surfaces. Eye Protection: Safety goggles or glasses, meeting BS EN 166 standards, must be worn during shot/grit blasting activities to protect against flying particles and debris. Hearing Protection: During shot/grit blasting, appropriate hearing protection, such as earplugs or earmuffs, must be used to safeguard against noise-induced hearing loss. Respiratory Protection: For tasks involving shot/grit blasting, operatives must wear respirators with filters suitable for dust and particulate matter, in accordance with BS EN 149 standards. All PPE must be regularly maintained and replaced as necessary to ensure its effectiveness. Compliance with these procedures is mandatory to ensure the safety and well-being of all personnel involved in rope access activities. In the event of an emergency during rope access activities, the following procedures must be strictly adhered to: Immediate Response: Upon identifying an emergency, the nearest team member must alert others by shouting "Emergency" and using a pre-agreed hand signal. All work must cease immediately. Communication: The designated team leader will contact the site emergency services using a two-way radio or mobile phone. Ensure that all team members are aware of the emergency contact numbers prior to commencing work. Rescue Plan Activation: A detailed rescue plan, specific to rope access activities, must be in place and rehearsed regularly. The rescue plan should include: First Aid: Administer first aid as necessary until professional medical assistance arrives. Ensure that at least one team member is trained in first aid specific to rope access injuries. Evacuation: If evacuation is required, ensure that all personnel are accounted for and moved to a designated safe area. The team leader must conduct a roll call to confirm that all individuals are present. Post-Incident Review: After the emergency has been resolved, conduct a thorough review of the incident to identify any procedural failures or areas for improvement. Document findings and update the method statement accordingly. Equipment Inspection: Post-incident, all equipment involved in the emergency must be inspected for damage or wear before being returned to service. It is imperative that all personnel involved in rope access activities are familiar with these procedures and participate in regular drills to ensure preparedness. All rope access activities will be conducted with the utmost consideration for the safety of the public and occupiers. The following procedures will be strictly adhered to: Exclusion Zones: Clearly marked exclusion zones will be established beneath all work areas to prevent unauthorised access by the public and occupiers. These zones will be demarcated using barriers and signage, ensuring visibility and understanding. Signage: Prominent warning signs will be displayed at all access points to the work area, indicating the presence of rope access activities and potential hazards. Signs will be maintained in a clean and legible condition throughout the duration of the project. Communication: A communication plan will be implemented to inform occupiers of the building about the nature and schedule of the rope access activities. This will include regular updates on progress and any changes to access arrangements. Spotters: Designated spotters will be employed to monitor the work area and ensure that no unauthorised persons enter the exclusion zones. Spotters will be equipped with communication devices to alert rope access technicians of any potential risks. Tool Management: All tools and equipment used during rope access activities will be securely tethered to prevent accidental dropping. Regular checks will be conducted to ensure that all equipment is in good working order and properly secured. Work Scheduling: Rope access activities will be scheduled during times of low occupancy or public presence, where feasible, to minimise disruption and risk to non-involved persons. Emergency Procedures: A comprehensive emergency response plan will be in place, detailing procedures for evacuating the area and providing assistance in the event of an incident. All personnel involved in rope access activities will be trained in these procedures. By adhering to these specific procedures, the safety of the public and occupiers will be prioritised throughout the execution of rope access activities. All personnel involved in rope access activities must be briefed on the potential presence of asbestos-containing materials (ACMs) prior to commencing work. A thorough review of the asbestos register and any relevant surveys must be conducted to identify areas where ACMs may be present. Pre-Work Assessment: Work Area Isolation: Emergency Procedures: Training and PPE: Communication: Documentation: Monitoring of rope access activities shall be conducted by a competent supervisor who possesses the necessary qualifications and experience in rope access operations. The supervisor shall ensure that all personnel adhere to the established safety protocols and procedures throughout the duration of the project. Daily inspections of all rope access equipment, including harnesses, ropes, and anchors, must be carried out prior to commencement of work. Any equipment found to be defective or showing signs of wear shall be immediately removed from service and replaced. Continuous observation of the work site is required to identify any potential hazards or changes in conditions that may affect the safety of the rope access activities. The supervisor shall maintain clear communication with all team members to promptly address any issues that arise. Regular audits of the work practises shall be conducted to ensure compliance with the method statement and risk assessments. Any deviations from the approved procedures must be documented, and corrective actions implemented without delay. Weather conditions must be monitored closely, as adverse weather can significantly impact the safety of rope access operations. Work shall be suspended if conditions become unsafe, such as high winds or heavy rain. The supervisor shall maintain a logbook documenting all monitoring activities, including equipment inspections, observations, audits, and any incidents or near misses. This logbook shall be reviewed regularly to identify trends and areas for improvement in safety practises. All waste generated during rope access activities, including shot/grit blasting and bird control installations, must be managed in accordance with the following procedures: Segregation and Collection: Waste materials, such as spent grit, bird netting offcuts, and packaging from bird spikes, must be segregated at the point of generation. Clearly labelled containers or bags should be used to collect each type of waste separately. Containment: Ensure that all waste is securely contained to prevent any debris from falling or being blown from height. This is particularly crucial during rope access operations where waste could pose a hazard to personnel below. Transportation: Waste must be carefully lowered to ground level using appropriate lifting techniques and equipment. This may include the use of rope systems or mechanical hoists, ensuring compliance with manual handling regulations. Disposal: Once at ground level, waste should be transferred to designated waste disposal areas or skips. Ensure that all waste is disposed of in accordance with local authority regulations and site-specific waste management plans. Documentation: Maintain accurate records of all waste types and quantities removed from the site. This documentation should be readily available for inspection and form part of the project’s environmental management records. Minimisation: Efforts should be made to minimise waste generation by optimising material usage and reusing materials where possible. This includes careful planning of bird netting and spike installations to reduce offcuts. Training: All personnel involved in rope access activities must receive training on these waste management procedures to ensure compliance and environmental protection. By adhering to these procedures, the project will ensure effective waste management specific to rope access activities, thereby minimising environmental impact and maintaining site safety. All personnel involved in rope access activities must ensure that environmental considerations are adhered to throughout the project. Minimising environmental impact is paramount, particularly given the nature of working at height and the potential for materials to fall or be dispersed. Containment of Materials: During shot/grit blasting, it is essential to use containment sheeting to prevent the spread of debris and dust. This will protect the surrounding environment and reduce the risk of contamination. Waste Management: All waste generated from shot/grit blasting, bird netting, and bird spike installation must be collected and disposed of in accordance with local regulations. Waste containers should be positioned at ground level, and waste should be lowered using appropriate lifting techniques to prevent spillage. Noise Control: Rope access activities, particularly shot/grit blasting, can generate significant noise. Efforts should be made to schedule such activities during times that minimise disturbance to nearby residents and wildlife. Use of noise-dampening equipment is recommended where feasible. Protection of Wildlife: When installing bird netting and spikes, care must be taken to ensure that no harm comes to local wildlife. Any nests found must be reported to the site manager, and work in those areas should be postponed until appropriate measures are taken. Spill Prevention: All equipment used in rope access activities must be checked for leaks or potential spills. Drip trays should be used where necessary, particularly when working with machinery or substances that could harm the environment if spilled. Training and Awareness: All operatives must receive training on environmental protection measures specific to rope access activities. This includes understanding the importance of minimising impact and the procedures for reporting any environmental incidents. By adhering to these procedures, the project will ensure compliance with environmental regulations while maintaining a commitment to sustainable practises. The project team shall ensure that all rope access activities are conducted with minimal disruption to near neighbours. Communication with adjacent property owners and occupants will be established prior to commencement of work to inform them of the nature and duration of the activities. Noise levels will be monitored and controlled, particularly during shot/grit blasting operations. Work will be scheduled during agreed hours to avoid disturbance during early mornings, late evenings, and weekends. Visual privacy will be respected by positioning operatives and equipment in a manner that does not intrude upon neighbouring properties. Dust and debris from shot/grit blasting will be contained using appropriate sheeting and barriers to prevent spread beyond the work area. Regular cleaning of the site perimeter will be conducted to maintain cleanliness and prevent nuisance. Access routes for operatives and equipment will be planned to avoid obstruction of neighbouring properties’ access points. In the event of any complaints or issues raised by neighbours, a designated contact person from the project team will address concerns promptly and effectively. Rope access activities necessitate stringent occupational health procedures to ensure the safety and well-being of all personnel involved. Personnel must undergo a comprehensive medical assessment to confirm their fitness for working at height and in potentially strenuous conditions. This assessment should be conducted by a qualified occupational health professional and include evaluations of cardiovascular health, musculoskeletal condition, and vertigo susceptibility. Regular breaks must be scheduled to prevent fatigue, which can significantly impair concentration and increase the risk of accidents. The work schedule should be structured to allow for adequate rest periods, particularly during tasks requiring sustained physical exertion such as shot/grit blasting. Hydration and nutrition are critical. Workers must have access to sufficient drinking water and be encouraged to maintain hydration throughout their shifts. Nutritional needs should be met with appropriate meal breaks, ensuring energy levels are sustained. Noise exposure from shot/grit blasting must be managed through the provision of suitable hearing protection. Regular monitoring of noise levels should be conducted to ensure compliance with exposure limits. Dust and particulate matter from blasting activities pose respiratory risks. Personnel must be equipped with appropriate respiratory protective equipment (RPE) and trained in its correct use. The effectiveness of RPE should be regularly checked, and fit testing conducted to ensure a proper seal. Manual handling risks associated with equipment and materials used in rope access tasks must be mitigated through training in safe lifting techniques and the use of mechanical aids where feasible. Mental health support should be available, recognising the psychological demands of working at height. Access to counselling services or mental health first aiders can provide necessary support. Finally, a robust incident reporting system must be in place to capture any health-related issues promptly, allowing for swift intervention and prevention of recurrence. All amendments to the method statement for rope access activities must be documented and authorised prior to implementation. Any proposed changes shall be communicated to the site supervisor, who will assess the impact on safety and operational efficiency. Key Procedures: Identification of Amendments: Risk Assessment Review: Consultation with Competent Persons: Authorisation Process: Communication of Changes: Documentation: Monitoring and Feedback: By adhering to these procedures, the integrity and safety of rope access activities are maintained throughout the project lifecycle.
Who might be harmed:
Rope access technicians | Site supervisors | Nearby workers on site
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Nearby workers
Type of harm:
Eye Damage
Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians
Type of harm:
Dermatitis
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Site supervisors | Nearby workers on site
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Asphyxia | Respiratory damage / Asthma / COPD | Smoke Inhalation
Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Site workers in proximity
Type of harm:
Illness | Death
Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians
Type of harm:
Eye Damage
Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians
Type of harm:
Dermatitis
Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Site workers in proximity
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians
Type of harm:
Illness
Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Maintenance personnel
Type of harm:
Eye Damage
Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Maintenance personnel
Type of harm:
Dermatitis
Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Nearby workers on site
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Nearby workers
Type of harm:
Eye Damage
Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Rope access technicians | Nearby workers
Type of harm:
Cuts and Abrasions | Dermatitis
Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.Site Specific Hazards
Falls from height : Low (1)
Falling objects : Low (1)
Suspension trauma : Low (1)
Equipment failure : Low (1)
Adverse weather conditions : Low (1)
Inadequate communication : Low (1)
Entrapment or entanglement : Low (1)
Inadequate training or competence : Low (1)
Procedures
Personnel and competence
Site inductions and training
Access and egress arrangements
Welfare
Special permits
Tools and equipment
Services and isolations
Hazardous substances
Deliveries and materials handling
PPE
Emergency procedures
Safety of public and occupiers
Asbestos
Before any rope access work begins, a visual inspection of the work area must be carried out by a competent person to confirm the absence of visible ACMs. If any suspect materials are identified, work must cease immediately, and the site supervisor must be informed.
The work area must be clearly demarcated and isolated to prevent unauthorised access. Warning signs indicating the potential presence of asbestos should be prominently displayed.
In the event that ACMs are disturbed during rope access activities, all work must stop immediately. Personnel must vacate the area and report the incident to the site supervisor. An emergency response plan must be in place, detailing the steps to safely manage and contain any asbestos release.
All operatives must have received asbestos awareness training. Appropriate personal protective equipment (PPE), including respiratory protective equipment (RPE), must be worn if there is any risk of exposure to asbestos fibres.
Clear communication channels must be established to ensure that all team members are aware of the procedures related to asbestos management. Regular briefings should be conducted to reinforce the importance of adhering to these procedures.
All findings, incidents, and actions taken regarding asbestos must be documented and reported in accordance with company policy and legal requirements. This documentation should be reviewed regularly to ensure compliance and to update procedures as necessary.Monitoring
Waste management
Environmental considerations
Near neighbours and nuisance
Occupational health
Amendments and authorisation
Any team member identifying a need for amendment must report it immediately to the site supervisor. This includes changes in techniques, equipment, or personnel that may affect the safety of rope access operations.
The site supervisor will conduct a thorough review of the existing risk assessment to determine if the proposed amendment introduces new hazards or alters existing ones. This review must be documented.
The site supervisor will consult with competent persons, such as a qualified rope access technician or health and safety advisor, to evaluate the feasibility and safety implications of the proposed amendment.
Once reviewed, the amendment must be authorised by the project manager or designated health and safety officer. Authorisation is contingent upon ensuring that all safety measures are maintained or enhanced.
All authorised amendments must be communicated to the entire rope access team during a toolbox talk before work commences. This ensures that all personnel are aware of the changes and understand their roles and responsibilities.
The amended method statement must be updated in writing, with a clear record of the changes made, the date of amendment, and the names of those authorising and implementing the changes.
Post-implementation, the site supervisor will monitor the effectiveness of the amendment and gather feedback from the rope access team to ensure that safety standards are upheld.Activities
Preparation and Setup
Equipment Inspection and Maintenance
Rope Access System Installation
Safety Briefing and Personnel Training
Shot/Grit Blasting Procedures
Bird Netting Installation Techniques
Bird Spike Installation Methods
Monitoring and Communication Protocols
Emergency and Rescue Procedures
Site Clean-up and Equipment Dismantling
Waste Disposal and Environmental Considerations
Final Inspection and Documentation
Hazardous Substances
Silica dust
Silica dust is not intended for use but is a by-product generated during the shot/grit blasting of substrates.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Lead-based paint
Lead-based paint is not intended for use in modern construction projects due to its hazardous nature and is typically encountered during the refurbishment or demolition of older structures.
Inhalation : Low (1)
Ingestion : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Bird droppings
Bird droppings are not intended for use; rather, they are a hazardous substance that workers may encounter during rope access activities, necessitating appropriate protective measures.
Inhalation : Low (1)
Ingestion : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Abrasive blasting media
Abrasive blasting media is utilised to clean and prepare the substrate surface by removing rust, paint, and other contaminants prior to further treatment or coating.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Induction Record
Company name:
Project title:
Location:
Contract No:
Subject:
Method Statement : Rope Access Activities
Tutor:
Date:
Signature:
Name Comments Signature Date