Risk Assessment and Method Statement Template for Prepare Area for Repointing Work
This document should not be used until it has been thoroughly reviewed by a competent person.
| Company name: | |
| Project title: | |
| Location: | |
| Contract No: | |
| Author: | |
| Reviewed by: | |
| Date: | |
| Signature: |
This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
Method Statement : Prepare Area for Repointing Work
Explanation
The preparation of an area for repointing work involves a series of methodical steps designed to ensure the integrity and safety of the structure while safeguarding the health and safety of the workforce. This process includes setting up appropriate access, such as scaffolding, to facilitate safe and efficient work at height. The task requires the careful raking out of old or loose pointing material, followed by its proper disposal to prevent environmental contamination and maintain a tidy worksite. Subsequently, the area is meticulously brushed to remove any residual debris, ensuring a clean surface for the new pointing material. Finally, the surface is dampened with water to optimise adhesion and minimise dust generation, thereby enhancing the quality and durability of the repointing work.
Responsibilities
- Site Supervisor: Ensure all safety protocols are followed and oversee the setup of access equipment.
- Scaffolder: Erect and inspect scaffolding to ensure it is safe and secure for use.
- Labourer: Rake out old or loose pointing and dispose of debris in accordance with waste management procedures.
- Cleaner: Brush the area to remove residue and ensure a clean surface for further work.
- Water Technician: Dampen the prepared area with water to minimise dust and prepare the surface for repointing.
Equipment
- Scaffold
- Ladder
- Trowel
- Hammer and chisel
- Wire brush
- Dustpan and brush
- Bucket
- Hose or spray bottle
- Safety helmet
- Safety goggles
- Dust mask or respirator
- Ear protection
- Gloves
- High-visibility vest
- Steel-toe boots
Operation
- Conduct a risk assessment to identify potential hazards and implement control measures.
- Ensure all personnel are trained and competent in the tasks they are to perform.
- Verify that all necessary personal protective equipment (PPE) is available and in good condition.
- Inspect the work area for any existing hazards, such as loose debris or uneven surfaces, and address them accordingly.
- Erect scaffolding by a competent person, ensuring it is stable, level, and securely anchored.
- Install guardrails and toe boards on the scaffolding to prevent falls and falling objects.
- Ensure safe access to the scaffolding, such as ladders or stair towers.
- Use appropriate tools to rake out old or loose pointing, ensuring they are in good condition.
- Wear suitable PPE, including safety goggles, gloves, and dust masks, during the raking process.
- Work methodically to remove only the loose or deteriorated mortar without damaging the brickwork.
- Collect all removed mortar and debris in designated containers or bags for disposal.
- Dispose of waste in accordance with local regulations and site-specific waste management procedures.
- Use a stiff-bristled brush to remove any remaining dust or loose particles from the joints.
- Lightly dampen the area with water using a low-pressure hose or spray bottle, ensuring not to saturate the brickwork.
- Confirm that the water source is safe and free from contaminants.
- Maintain a clean work area by regularly removing debris to prevent trip hazards.
- Secure the work area with appropriate signage and barriers to prevent unauthorised access.
- Establish a clear communication plan among team members, including emergency procedures.
- Ensure that a first aid kit is readily accessible and that personnel are aware of its location.
Risk Assessment : Prepare Area for Repointing Work
Working at Height : Low (1)
Who might be harmed: Construction Workers | Scaffolders | Site Supervisors
Type of harm: Broken Bones | Death | Head Injury | Multiple / Various Injury
Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | Labourers | Maintenance Personnel | Subcontractors
Type of harm:
Back / Spinal Injury | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Muscular Injury
Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | Site Supervisors | Nearby Personnel
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD
Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | Site Supervisors | Nearby Personnel
Type of harm:
Permanent Hearing Damage
Initial Risk: Major (3) x Probable (4) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | Maintenance Personnel
Type of harm:
Cuts and Abrasions
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | Site Supervisors | Visitors to the Site | Delivery Personnel | Subcontractors
Type of harm:
Back / Spinal Injury | Broken Bones | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury | Muscular Injury
Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | Electricians | Site Supervisors | Maintenance Personnel
Type of harm:
Burns | Death | Electrocution
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | Contractors or Subcontractors
Type of harm:
Eye Damage
Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | Site Supervisors
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Burns | Dermatitis | Respiratory damage / Asthma / COPD
Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction Workers | Site Supervisors | Maintenance Personnel
Type of harm:
Cold / Pneumonia | Drowning
Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers | Site supervisors | Nearby workers from other trades
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD
Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers
Type of harm:
Eye Damage
Initial Risk: Catastrophic (5) x Occasional (3) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers | Maintenance personnel
Type of harm:
Dermatitis
Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers directly involved in the preparation work. | Nearby workers on site.
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD
Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers | Site supervisors
Type of harm:
Eye Damage
Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers | Labourers | Maintenance personnel | Clean-up crew
Type of harm:
Dermatitis
Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed:
Construction workers | Site supervisors | Nearby workers from other trades | Maintenance personnel
Type of harm:
Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD | Death
Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
The preparation of an area for repointing work involves a series of methodical steps designed to ensure the integrity and safety of the structure while safeguarding the health and safety of the workforce. This process includes setting up appropriate access, such as scaffolding, to facilitate safe and efficient work at height. The task requires the careful raking out of old or loose pointing material, followed by its proper disposal to prevent environmental contamination and maintain a tidy worksite. Subsequently, the area is meticulously brushed to remove any residual debris, ensuring a clean surface for the new pointing material. Finally, the surface is dampened with water to optimise adhesion and minimise dust generation, thereby enhancing the quality and durability of the repointing work. The preparation area for repointing work presents several hazards that must be carefully managed to ensure the safety of all personnel involved. The erection and use of scaffolding pose risks of falls from height, which necessitates proper installation and use of fall protection measures. The process of raking out old or loose pointing can generate dust, potentially containing hazardous materials such as silica, which requires appropriate respiratory protection and dust control measures. Manual handling of tools and materials can lead to musculoskeletal injuries if not performed with correct techniques. Additionally, the use of sharp tools for raking out mortar presents a risk of cuts or abrasions. The disposal of debris must be conducted safely to prevent trips and slips, while brushing to remove residue can further contribute to airborne dust hazards. Finally, dampening the area with water introduces the potential for slips, necessitating caution and the use of non-slip footwear. This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
Manual Handling : Low (1)
Dust Inhalation : Low (1)
Noise Exposure : Low (1)
Sharp Tools : Low (1)
Slips, Trips, and Falls : Low (1)
Electric Shock : Low (1)
Eye Injuries : Low (1)
Chemical Exposure : Low (1)
Water Hazards : Low (1)
COSHH Assessment : Prepare Area for Repointing Work
Silica dust
Silica dust is not an intended substance for use; rather, it is a by-product generated during the cutting, grinding, or drilling of materials such as concrete, brick, and mortar.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Cement dust
Cement dust is generated during the handling and mixing of cement-based materials used to prepare surfaces for repointing work.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Asbestos (if present in older buildings)
Asbestos, if present in older buildings, was historically used for its fire-resistant and insulating properties.
Inhalation : Low (1)
Toolbox Talk : Prepare Area for Repointing Work
Introduction
Hazards
Prepare Area for Repointing Work : Rules
Prepare Area for Repointing Work : Warnings
Induction Record
Company name:
Project title:
Location:
Contract No:
Subject:
Risk Assessment and Method Statement : Prepare Area for Repointing Work
Tutor:
Date:
Signature:
Name Comments Signature Date

