Method Statement : Cleaning of Roof
Explanation
The cleaning of roofs using a pressure washer with long reach poles and a rotary surface cleaner is a task aimed at maintaining the structural integrity and aesthetic appearance of the roof. This process involves the removal of dirt, debris, moss, and algae that can accumulate over time, potentially causing damage or reducing the lifespan of the roofing materials. The operation is conducted from ground level or a scaffold tower to ensure safety while providing effective cleaning. The use of specialised equipment allows for thorough cleaning without the need for direct access to the roof surface, thereby minimising the risk of falls and other associated hazards.
Responsibilities
- Site Manager: Ensure all safety protocols and procedures are in place and adhered to during the roof cleaning process.
- Health and Safety Officer: Conduct risk assessments and ensure compliance with health and safety regulations.
- Supervisor: Oversee the cleaning operation, ensuring that all workers are following safe working practises.
- Operative: Use pressure washers and equipment safely, adhering to training and instructions provided.
- Equipment Inspector: Check all equipment, including pressure washers and scaffold towers, for safety and functionality before use.
- First Aider: Provide immediate medical assistance in case of an accident or injury on site.
Equipment
- Pressure washer
- Long reach poles
- Rotary surface cleaner
- Scaffold tower
- Safety harness
- Hard hat
- Non-slip footwear
- Safety goggles
- Gloves
- High-visibility clothing
Operation
- Conduct a risk assessment to identify potential hazards and implement control measures.
- Ensure all personnel involved are trained and competent in the use of pressure washers and working at height.
- Inspect the roof for structural integrity and any potential hazards, such as loose tiles or debris.
- Verify weather conditions are suitable for roof cleaning activities.
- Inspect all equipment, including pressure washers, long reach poles, and rotary surface cleaners, for any damage or defects.
- Set up appropriate access equipment, such as scaffold towers, ensuring they are stable, secure, and comply with safety standards.
- Establish a safe work area by cordoning off the site with warning signs and barriers to prevent unauthorised access.
- Ensure all necessary personal protective equipment (PPE) is available and worn by workers, including helmets, gloves, eye protection, and non-slip footwear.
- Identify and mark any overhead power lines or electrical hazards in the vicinity.
- Develop an emergency plan, including procedures for rescue in the event of a fall or other incident.
- Communicate the plan and safety procedures to all personnel involved in the task.
- Conduct a test run of the pressure washer and rotary surface cleaner to ensure they are functioning correctly.
- Begin cleaning from the highest point of the roof and work downwards, maintaining a safe distance from the edge.
- Use controlled movements to avoid overreaching or losing balance while operating the equipment.
- Continuously assess weather conditions for any changes that may affect safety, such as increased wind or rain.
- Maintain clear communication with team members throughout the task to ensure coordination and address any issues promptly.
- Take regular breaks to prevent fatigue, especially when working in extreme temperatures or for extended periods.
- Once cleaning is complete, carefully disassemble equipment and inspect for any damage.
- Ensure the work area is left clean and free of hazards.
- Conduct a post-task review to evaluate the task and identify any areas for improvement in safety procedures or equipment use.
Risk Assessment : Cleaning of Roof
Falls from height : Low (1)
Who might be harmed: Roof cleaning operatives | Scaffold tower users | Maintenance personnel
Type of harm: Back / Spinal Injury | Broken Bones | Death | Head Injury | Multiple / Various Injury
Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives | Scaffold tower users Type of harm: Back / Spinal Injury | Broken Bones | Cuts and Abrasions | Death | Head Injury | Multiple / Various Injury | Muscular Injury Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives | Scaffold tower assemblers | Equipment handlers Type of harm: Back / Spinal Injury | Broken Bones | Crush / Entrapment | Cuts and Abrasions | Muscular Injury Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives | Nearby workers Type of harm: Burns | Dermatitis | Eye Damage | Respiratory damage / Asthma / COPD Initial Risk: Severe (4) x Frequent (5) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives | Scaffold tower users | Ground-level workers Type of harm: Burns | Death | Electrocution Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives | Scaffold tower users Type of harm: Cold / Pneumonia | Heat Stroke / Exhaustion | Illness Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives | Maintenance personnel | Scaffold tower users Type of harm: Crush / Entrapment | Broken Bones | Death | Head Injury Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives | Scaffold tower users | Ground-level workers | Bystanders or pedestrians Type of harm: Cuts and Abrasions | Electrocution | Eye Damage | Head Injury | Permanent Hearing Damage Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives | Nearby workers on site Type of harm: Permanent Hearing Damage Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives | Ground-level workers | Bystanders or pedestrians Type of harm: Cuts and Abrasions | Eye Damage | Head Injury Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning workers Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Asphyxia | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Severe (4) x Probable (4) = Medium (16)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives Type of harm: Eye Damage Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning operatives Type of harm: Burns | Dermatitis Initial Risk: Severe (4) x Occasional (3) = Medium (12)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning workers | Nearby site personnel | Occupants of the building Type of harm: Asbestosis / Lung Cancer / Mesothelioma | Respiratory damage / Asthma / COPD | Smoke Inhalation Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning workers | Maintenance personnel Type of harm: Eye Damage Initial Risk: Major (3) x Frequent (5) = Medium (15)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning workers | Maintenance personnel Type of harm: Dermatitis Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning workers | Maintenance personnel Type of harm: Respiratory damage / Asthma / COPD Initial Risk: Major (3) x Occasional (3) = Medium (9)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning workers Type of harm: Illness Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning workers Type of harm: Eye Damage Initial Risk: Catastrophic (5) x Probable (4) = High (20)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
Who might be harmed: Roof cleaning personnel Type of harm: Dermatitis Initial Risk: Catastrophic (5) x Frequent (5) = High (25)
Controls
Residual Risk: Minor (1) x Improbable (1) = Low (1)
The cleaning of roofs using a pressure washer with long reach poles and a rotary surface cleaner is a task aimed at maintaining the structural integrity and aesthetic appearance of the roof. This process involves the removal of dirt, debris, moss, and algae that can accumulate over time, potentially causing damage or reducing the lifespan of the roofing materials. The operation is conducted from ground level or a scaffold tower to ensure safety while providing effective cleaning. The use of specialised equipment allows for thorough cleaning without the need for direct access to the roof surface, thereby minimising the risk of falls and other associated hazards. The primary hazards associated with cleaning a roof using a pressure washer with long reach poles and a rotary surface cleaner include the risk of falls from height, particularly when working from a scaffold tower. There is also a significant risk of slips, trips, and falls due to wet and slippery surfaces. Manual handling hazards arise from lifting and manoeuvring the equipment, which can lead to musculoskeletal injuries. The use of high-pressure water jets poses a risk of injury if not handled correctly. Additionally, there is potential exposure to hazardous substances from cleaning agents. Electrical hazards must be considered, especially in proximity to overhead power lines or electrical installations. Weather conditions such as wind or rain can further exacerbate these risks, while ensuring safe access and egress is crucial to prevent accidents. Proper training, supervision, and the use of appropriate personal protective equipment are essential to mitigate these dangers. This document has been provided as a template. By completing the section above, you take full responsibility for the use of this document.
Slippery surfaces : Low (1)
Manual handling : Low (1)
Chemical exposure : Low (1)
Electrical hazards : Low (1)
Weather conditions : Low (1)
Structural integrity : Low (1)
Equipment malfunction : Low (1)
Noise exposure : Low (1)
Flying debris : Low (1)
COSHH Assessment : Cleaning of Roof
Cleaning chemicals
Cleaning chemicals are intended to effectively remove dirt, debris, and organic growth from roof surfaces, ensuring a clean and safe environment.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Mould and mildew
Mould and mildew are not intended for use; rather, they are biological hazards that may be encountered on roofs, requiring careful removal to prevent health risks.
Inhalation : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Bird droppings
Bird droppings are not intended for use; rather, they are a potential hazard during roof cleaning due to the presence of harmful pathogens that can lead to respiratory illnesses.
Inhalation : Low (1)
Ingestion : Low (1)
Eye Contact : Low (1)
Skin Contact : Low (1)
Toolbox Talk : Cleaning of Roof
Introduction
Hazards
Cleaning of Roof : Rules
Cleaning of Roof : Warnings
Induction Record
Company name:
Project title:
Location:
Contract No:
Subject:
Risk Assessment and Method Statement : Cleaning of Roof
Tutor:
Date:
Signature:
Name
Comments
Signature
Date